the Education Authority: Contract Register & Procurement Profile

Central governmentNorthern IrelandBelfastRan 1 procurement for other authorities

Official UK PPONPPHJ-6982-JPXY

Open now3next deadline 9 Nov 2026
i

Tenders you can still bid for.

Notices at tender stage whose deadline has not passed, counted the way the search counts them: a notice shows under every code and region it names.

Notices, last 12 months87-17% vs prior 12 months (105)
i

Notices published in the last 12 months.

Counted per tender, not per lot, against the 12 months before where shown.

Typical bids per lot423.8% single-bid · 42 bid reports
i

How many companies usually bid when this buyer runs a tender.

Middle value of the bid counts on its award notices, one per lot. Only real competitions count: direct awards and framework places are left out.

Based on 42 lots from this buyer’s competitions, last 24 months.

Last 24 months, all categories.

Top-3 supplier share15%of 255 awarded procedures · 387 suppliers
i

How much of this buyer’s work goes to its three most frequent suppliers.

Share of its awarded tenders that name at least one of the top three. Each tender is counted once.

255 awarded tenders, 387 different suppliers.

Describes the record. It is not a sign of favouritism.

All awards we hold.

Contracts ending ≤18 months8723 within 6 months · 72 estimated
i

Contracts that finish in the next 18 months.

Contracts ending in that window by the published end date or, where only a duration is published, an estimate from signature plus duration (marked). Neither, not counted.

An end date does not confirm a new procurement.

Published award value, 24m£2.5bnnet · on 100 of 103 published values · 3 repeated amounts set aside · top 5 = 71%
i

How much this buyer has awarded recently, by published values.

Sum of published VAT-exclusive awards to single suppliers, last 24 months. Left out: concession revenue, framework ceilings, repeated notices, equal-value duplicates.

Published values, not actual spend. The biggest rows are listed so you can check.

Open notices

3 live · deadline in the future or not published · as of page build

NoticeDeadlineDays leftPublished value
Fixed Asset Management System9 Nov 202611d£800,000
TRN-24-002 Transport of School MealsDPScentral purchasing body11 lots7 Jul 2028617d£21,000,000

All 3 open notices for this authority →

What they buy
i

What kind of work is bought here.

Notices by procurement category (CPV). A notice with several categories counts in each.

Last 24 months · CPV divisions on published procedures · a notice with several divisions counts in each

How they buy
i

How work here is packaged.

Notices by commercial tool: a single contract, a framework, or a dynamic purchasing system.

Last 24 months · 192 notices · commercial tool and route as published on the notice, not a legal-regime claim

Commercial tool
i

How work here is packaged.

Notices by commercial tool: a single contract, a framework, or a dynamic purchasing system.

  • Contract85%(163 notices)
    163 of 192 notices are Contract (85%).
  • Framework14%(26 notices)
    26 of 192 notices are Framework (14%).
  • Dynamic purchasing system2%(3 notices)
    3 of 192 notices are Dynamic purchasing system (2%).
Procedure route
i

Which procedures buyers here use.

Notices by the procedure they declare: open, selective, limited or direct. Open and selective are competitions; limited and direct are not.

  • Limited / restricted26%(49 notices)
    49 of 192 notices are Limited / restricted (26%).
  • Open26%(49 notices)
    49 of 192 notices are Open (26%).
  • Route not published24%(47 notices)
    47 of 192 notices are Route not published (24%).
  • Selective22%(42 notices)
    42 of 192 notices are Selective (22%).
  • Direct award3%(5 notices)
    5 of 192 notices are Direct award (3%).
Typical bids per lot
i

How many companies usually bid when this buyer runs a tender.

Middle value of the bid counts on its award notices, one per lot. Only real competitions count: direct awards and framework places are left out.

Based on 42 lots from this buyer’s competitions, last 24 months.

Last 24 months, all categories.

4robust · n=4223.8% of lots drew a single bid
Deadline → award
i

How long this buyer takes to decide after bids close.

Middle value in days from the bid deadline to the award date, on this buyer’s own tenders.

Based on 32 decided tenders across all categories, last 24 months.

Last 24 months.

45 daysrobust · n=32
Notice amendments
i

How often this buyer changes a notice after publishing it.

Middle number of amendments per notice. Deadline extensions and corrections both count.

Based on 192 notices across all categories, last 24 months.

Last 24 months.

062 of 192 notices amended
Award vs estimate
i

Do this buyer’s awards land above or below its own estimates.

Each lot’s published estimate against its award, on this buyer’s competitions, like for like.

Based on 27 lots with both an estimate and an award, last 24 months.

A past pattern, not a price to bid.

Last 24 months.

0% at estimaterobust · n=27

Who wins here
i

Which suppliers win the most here.

Suppliers ranked by the number of tenders won, not by money. A supplier on one big framework with many call-offs does not outrank one that won many separate competitions.

All published awards naming a supplier · ranked by distinct procedures, not pounds · panel and call-off entries inflate award records

SupplierProceduresShareLast 24mAward recordsLast activity
Irwin ME Ltd166.3%528—
Maurice Flynn and Sons Ltdframework/DPS on 1135.1%421—
Stephens Catering Equipment Co Ltdframework/DPS on 7114.3%22018 Feb 2026
Greystone Joinery Construction Ltdframework/DPS on 1103.9%318—
Henderson Foodservice Limitedframework/DPS on 483.1%33223 Feb 2026
CHC Group Ltd83.1%315—
MASSEY CATERING EQUIPMENT LIMITEDframework/DPS on 483.1%213—
Woodvale Construction Company83.1%211—

The three most frequent suppliers are named on 15% of 255 awarded procedures (each procedure counted once, so a panel shared by several of them is not double-counted); 387 distinct suppliers hold at least one. Descriptive concentration of published awards, not a statement of preference.

Published award value (24m)
i

How much this buyer has awarded recently, by published values.

Sum of published VAT-exclusive awards to single suppliers, last 24 months. Left out: concession revenue, framework ceilings, repeated notices, equal-value duplicates.

Published values, not actual spend. The biggest rows are listed so you can check.

£2.5bnSum of published VAT-exclusive values on 100 of 103 published single-supplier values; the five largest make 71%; a further 1 published a VAT-inclusive amount only, kept apart.
Typical single-supplier award (24m)
i

The middle published award value for this buyer.

Middle value of the same awards as the total above.

Last 24 months.

£2.5m middle valuerobust · n=100Middle half £460k–£7.2m; 3 awards with ambiguous equal values within a procedure excluded from both figures.
Largest published awards
i

The biggest published awards.

Awards to a single supplier with a published value, largest first, so you can check the totals against the notice.

A repeated framework total can appear here. Open the notice to check.

SupplierAwardedTermPublished value
Education Network for Northern Ireland - "Education Network (NI)"Capita Managed IT Solutions——£721,000,000 †
Education Network for Northern Ireland - "Education Network (NI)"Capita Managed IT Solutions——£721,000,000 †
Education Network for Northern Ireland - "Education Network (NI)"Capita Managed IT Solutions——£175,000,000 †
Provision of Planned and Responsive Maintenance and Minor Works - Armagh M&E Lot 2 Reference number Armagh M&E Lot 2CHC Group Ltd—3.8 yrs£131,265,000 †
≈ £34m/yr
Provision of Planned and Responsive Maintenance and Minor Works - Belfast Building Lot 1 Reference number Belfast Building Lot 1Maurice Flynn and Sons Ltd—3.8 yrs£66,150,000 †
≈ £17m/yr

Contracts ending
i

Contracts that finish in the next 18 months.

Contracts ending in that window by the published end date or, where only a duration is published, an estimate from signature plus duration (marked). Neither, not counted.

An end date does not confirm a new procurement.

453 of 570 contracts carry an end date, 290 estimated from the duration · not a retender forecast

Soonest 10 of 87 contracts ending within 18 months.

Recent procedures

Latest 50 of 381 procedures where this authority buys, is the authority the work is for, or runs the procurement

ProcedureStatusPublishedPublished value
Pre-Market Engagement Questionnaire: Tree Surgery and Tree SurveyingForestry and logging productsPlanning28 Aug 2026£6,400,000
EA Integrated Financial Management Information System Inc. HR/Payroll (Formerly the iFS Project / now known as the EA One Project)System and support servicesAwarded / complete27 Aug 2026—
Managed Support Services for EAConnect, NISTR & PSEP & DEIT services: consultingAwarded / complete18 Aug 2026—
Re-Tender for the Provision of Vehicle Bodywork and Accident Repair ServicesFramework4 lotsBus repair servicesOpen17 Aug 2026£1,530,000
Specialist Furniture and Equipment for Pupils with Special Educational NeedsFrameworkFurniture (incl. office furniture)Planning13 Aug 2026£0
Financial Management Solution and School Fees Management Solution for Voluntary Grammar and Grant Maintained Integrated SchoolIT services: consultingAwarded / complete13 Aug 2026£3,920,000
Provision of Vehicle Bodywork and Accident Repair ServicesFramework4 lotsBus repair servicesAwarded / complete12 Aug 2026£1,530,000
Online PaymentsDPSIT services: consultingOpen7 Aug 2026£15,000,000
***Pre-Market Engagement*** ICT-26-002 Tachograph Analysis and SupportRoad transport servicesOpen3 Aug 2026£360,000
Appointment of Integrated Supply team for Antrim Primary SchoolBuilding construction workOpen31 Jul 2026£5,200,000
Appointment of Integrated Consultant Team for St Patrick’s Grammar School Armagh - Upgrade of Heating SystemArchitectural and related servicesOpen30 Jul 2026£432,066
Appointment of Integrated Consultant Team for Longstone SchoolArchitectural and related servicesOpen27 Jul 2026£2,500,000
Appointment of Integrated Consultants Team for Jones Memorial Primary School, EnniskillenArchitectural and related servicesPlanned27 Jul 2026£153,300
Appointment of an Integrated Supply Team for Iveagh Primary SchoolBuilding construction workOpen27 Jul 2026£7,000,000
Delivery of a BTEC Level 3 National Diploma in Sport and a BTEC Level 3 National Certificate in Coaching and Development for St. Colm's High SchoolEducation and training servicesAwarded / complete27 Jul 2026£284,000
ID 1032027/L8 Legal Services for Strategic Partner Services & School Management System Solution ProjectLegal servicesAwarded / complete24 Jul 2026—
Provision of a Teacher Professional Learning SystemComputer platformsOpen24 Jul 2026£13,500,000
Appointment of Integrated Consultant Team for St. Gerard’s School, BelfastArchitectural and related servicesOpen24 Jul 2026£1,800,000
Outdoor Furniture made from Recycled PlasticFramework5 lotsBinsAwarded / complete24 Jul 2026£990,000
Appointment of an Integrated Consultant Team for a New Build Special School in South Belfast (Belfast SEN03)Architectural and related servicesOpen20 Jul 2026£4,000,000

Search all 381 procedures for this authority →

About this data
  • Source. Official UK public procurement notices (Find a Tender), reused under the Open Government Licence v3.0. New notices arrive through the day; the figures are rebuilt nightly.
  • One profile per authority. Different spellings and registration numbers of the same body are merged into this profile. It includes tenders the authority ran for other bodies and tenders run on its behalf; spend is credited to the body that pays.
  • Values are published values. Award values are what the authority published, excluding VAT and framework ceilings. They are not a budget or total spend.
  • Contract end dates. 453 of 570 published contracts have an end date; 290 of those are estimated as the signature (or publication) date plus the published duration and are marked “estimated”. They feed “Contracts ending”, the same rule as the retender radar.
  • Every figure shows what it rests on. Not every notice publishes a bid count, a value or a delivery region, so each figure carries the number of records behind it, and one built on few records is marked as such. The on a figure explains it; the counting rules are in the methodology. Spotted something wrong? Tell us.