Aggregate supply and track excavated waste
Authority: NETWORK RAIL INFRASTRUCTURE LIMITED (Central government)
What is being bought2 lots · detail below
Published requirement descriptionNetwork Rail is seeking to establish a national framework for the supply of aggregates (including blended ballast), the management of track excavated waste (hazardous and non-hazardous), and associated rail haulage services to and from Network Rail Aggregate Handling Depots (AHDs). The framework will support the provision of materials and services required for the maintenance, renewal and enhancement of the railway infrastructure across Great Britain.
The procurement is divided into two Lots, each comprising a group of AHD locations. Tenderers may submit a bid for one or both Lots. Network Rail intends to award two framework contracts, with one supplier appointed to each Lot. Where the same Tenderer achieves the highest overall score for both Lots, the Tenderer's stated Lot preference will be applied and the remaining Lot will be awarded to the next highest-scoring eligible Tenderer. Further details of the Lot structure and AHD locations are set out in the procurement documents.
The framework also includes provision for the future implementation of Aggregate Handling Depot (AHD) operational services at designated locations. These services will not commence automatically at the framework start date. Where Network Rail elects to introduce AHD operational services during the framework term, the scope, implementation arrangements and associated charges will be agreed in accordance with the framework contract provisions. Further details are set out in the procurement documents.
Network Rail reserves the right to amend the composition of the Lots during the procurement process, including the removal of an AHD where required. Any such change will be communicated through the procurement documentation and conducted in accordance with the Procurement Act 2023.
NOTE: The estimated framework value represents the total potential value across all Aggregate Handling Depots (AHDs) and the maximum framework term, including any extension option. The value is based on forecast demand and includes appropriate contractual headroom. It does not represent a guaranteed spend, minimum volume commitment, or value payable to any individual supplier. Following award, requirements will be allocated between the successful suppliers in accordance with their awarded Lot.
- How the procedure runs: Network Rail will undertake a Competitive Flexible Procedure comprising a Procurement Specific Questionnaire (PSQ) stage followed by a single tender stage. Tenderers may submit a bid for Lot 1, Lot 2 or both Lots. Following evaluation of technical and commercial submissions in accordance with the published evaluation methodology, Tenderers will be ranked based on their combined technical and commercial scores for each Lot. A maximum of one Lot may be awarded to any Tenderer. Where the same Tenderer achieves the highest score for both Lots, the Tenderer’s stated Lot preference will be applied and the remaining Lot will be awarded to the next highest-scoring eligible Tenderer. Two framework contracts will be awarded, one for each Lot. Further details are set out in the procurement documents.
CPV: Ballast · Gravel, sand, crushed stone and aggregates
How this framework works
From the published notice- Type
- Closed framework
- Call-offs
- call-offs are awarded directly to appointed suppliers, without further competition
- Places
- up to 2 suppliers
- Framework period
10 yrs · up to 15 yrs from 1 Apr 2028, The framework term exceeds the standard eight-year maximum due to the substantial capital and infrastructure investment required from suppliers to establish and maintain the rail-linked processing, blending and recycling capabilities necessary for contract delivery. Market engagement identified that suppliers would be unlikely to recover these investments within an eight-year term. A framework term of ten years, with an option to extend for up to a further five years, is therefore considered necessary to support investment, ensure ongoing market participation and competition, and facilitate the achievement of the framework's operational and sustainability objectives.
Published description of the framework
The framework will operate on a direct award basis. Two suppliers will be appointed, with each supplier allocated responsibility for a defined Lot comprising several Aggregate Handling Depots (AHDs). Contracts under the framework will be awarded directly to the supplier responsible for the relevant Lot and associated AHDs.
Pricing will be established through the tender process, with Tenderers submitting pricing for each Lot bid for in accordance with the Pricing Document. Pricing will include rates broken down by individual Aggregate Handling Depot (AHD), together with other pricing components specified in the procurement documents. The agreed prices will form the framework charges and will apply to Contract Orders issued under the framework, subject to any price adjustment mechanism set out in the framework terms and conditions.
Network Rail will issue Contract Orders under the framework to instruct the relevant Deliverables. A Contract Order will be issued on commencement of the framework to facilitate ordering and payment, with a new Contract Order issued for each Contract Year. Forecast quantities will be provided at the start of each Contract Year but will be indicative only and will not constitute a guarantee of demand or a commitment to purchase any minimum volume.
No further competition will be undertaken for the award of contracts under the framework.
Lots and requirements (2)Procurement structure
2 lots · all with a published value · win at most 1 of them · same conditions of participation on every lot · same evaluation weights on every lotEvery one of these 2 lots carries the same published figure, £1,064,000,000: it is the framework's maximum for the whole notice, not each lot's own budget, and no share per lot is published. The cards below say ceiling above rather than repeat it.
Lot #1AHD Group ARenewalceiling above
Provision of aggregate supply, track excavated waste management and associated rail haulage services for the following Aggregate Handling Depots (AHDs): Kingmoor, Doncaster, Crewe and Bescot.
- Condition of participationshortlisting
Suppliers will be shortlisted based on the outcome of the Procurement Specific Questionnaire (PSQ). Only suppliers that satisfy the exclusion grounds checks, meet all conditions of participation and achieve a pass on all pass/fail questions will be considered. The six highest-scoring suppliers, ranked according to their total weighted PSQ score, will be invited to participate in the tender stage.
Lot #2AHD Group BRenewalceiling above
Provision of aggregate supply, track excavated waste management and associated rail haulage services for the following Aggregate Handling Depots (AHDs): Westbury, Whitemoor, Eastleigh and Toton.
- Condition of participationshortlisting
Suppliers will be shortlisted based on the outcome of the Procurement Specific Questionnaire (PSQ). Only suppliers that satisfy the exclusion grounds checks, meet all conditions of participation and achieve a pass on all pass/fail questions will be considered. The six highest-scoring suppliers, ranked according to their total weighted PSQ score, will be invited to participate in the tender stage.
What it takes to wini
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Evaluation split and conditions of participation as published; the tender pack may add morei
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Published sub-criteria (2)
- Technical: 50%
- Price: 50%
Published award criteria (2)
- Technical: Assessment of the tenderer's technical submission, including future operational delivery model, management of ballast supply and track excavated waste services, sustainability, social value, safety, resilience, capability and delivery arrangements, in accordance with the procurement documents.
- Price: Tenderers shall submit pricing for each Lot bid for, in accordance with the Pricing Document. Prices will include rates broken down by individual Aggregate Handling Depot (AHD), together with the other pricing components and volume-based pricing requirements specified in the Pricing Document. Commercial scores will be calculated using the published proportional pricing methodology, whereby the lowest priced compliant submission for each Lot receives the maximum commercial score and all other compliant submissions are scored proportionally against it.
- Condition of participationshortlisting
Suppliers will be shortlisted based on the outcome of the Procurement Specific Questionnaire (PSQ). Only suppliers that satisfy the exclusion grounds checks, meet all conditions of participation and achieve a pass on all pass/fail questions will be considered. The six highest-scoring suppliers, ranked according to their total weighted PSQ score, will be invited to participate in the tender stage.
- Price carries 50 of 100 points: a 10% discount moves about 5 points. This one is won on the number: sharpen the price before polishing the prose.
- “Aggregate supply and track excavated waste” is a framework: the contest is a place on its panel, up to 2 suppliers, not a single contract, and call-offs are awarded directly: getting appointed is the whole game.
Price arithmetic assumes straight proportional scoring; the tender pack may use another formula.
Procedure terms & legal framework
From the official record- Procedure method
- Competitive flexible procedure
- Legal basis
- UKPGA · 2023/54 Procurement Act 2023
- Procurement category
- Goods
- Notice status
- Closed
- Procurement threshold
- Above threshold (FTS publication)
- Regulatory regime
- Utilities
- Commercial structure
- Framework agreement
- Who may use this agreement
- Not stated in the notice; call-off rights may be limited to the establishing authority
- Competition type
- Competitive procedure
- GPA / WTO covered
- Yes (GPA, CPTPP)
- Recurring procurement
- Unspecified in notice
- First published
- 2 Jun 2025, 16:58 BST
- Last source update
- 22 Sept 2026, 15:34 BST
- Award evaluation window
- Submission end – 21 Jun 2027
- Authority reference
SR40325- FTS notice number
2026/S 000-089760- Latest notice
- Tender notice (UK4)
- Classification (CPV)
- Delivery area
- Official registry OCID
ocds-h6vhtk-052b08Find a Tender
- How it runs
Network Rail will undertake a Competitive Flexible Procedure comprising a Procurement Specific Questionnaire (PSQ) stage followed by a single tender stage.
Tenderers may submit a bid for Lot 1, Lot 2 or both Lots.
Following evaluation of technical and commercial submissions in accordance with the published evaluation methodology, Tenderers will be ranked based on their combined technical and commercial scores for each Lot.
A maximum of one Lot may be awarded to any Tenderer. Where the same Tenderer achieves the highest score for both Lots, the Tenderer’s stated Lot preference will be applied and the remaining Lot will be awarded to the next highest-scoring eligible Tenderer.
Two framework contracts will be awarded, one for each Lot.
Further details are set out in the procurement documents.
How it was run
Official notice- Requests to participate (first stage)
- 21 Oct 2026, 17:00 BST
- Appointment period ends
- 21 Oct 2026, 17:00 BST
- Clarification deadline
- 13 Oct 2026, 17:00 BST
- Submission channel
- Official e-sourcing portal
- Electronic submission
- Allowed
- Accepted languages
- en
Timeline
2 Jun 2025 → 1 Apr 2028 · 7 dates- Planning notice published2 Jun 2025, 16:58 BST
- Next notice expected1 Jul 2025, 23:59 BST
- Tender notice published35 days ago22 Sept 2026, 15:34 BST
- Clarification questions by14 days ago13 Oct 2026, 17:00 BST
- Admission / appointment period ends6 days ago · period end, not a bid countdown21 Oct 2026, 17:00 BST
- Today28 Oct 2026
- Award decision expected byin 236 days21 Jun 2027, 23:59 BST
- Contract starts1 Apr 2028, 00:00 BST
Notice history
5 events · 2 releases on Find a Tender · since 2 Jun 2025- Pipeline notice published2 Jun 2025, 16:58 BSTUK1
- Tender notice published22 Sept 2026, 15:34 BSTUK4
- Published value updated to £1,064,000,00022 Sept 2026, 15:34 BSTwas £240,000,000
- Status changed to active22 Sept 2026, 15:34 BST
- Procurement method changed22 Sept 2026, 15:34 BST
Contracting authority & participating public bodies
Official documents & specifications (3)
Official links; attachments are not copiedTender pack and attachments
- Bidding documents and specificationsAccess: Additional procurement documents may be issued during the procurement process through the Network Rail Sourcing Platform (Bravo). This includes documents to be provided to shortlisted suppliers at the tender stage, together with the Lease and Sub-Lease documents referenced within the procurement documentation.