Official UK procurement notice
Chilled Goods · UK public procurement notice
Authority: The Common Services Agency (more commonly known as NHS National Services Scotland) (NSS) (NHS & healthcare)
What is being bought
Published requirement descriptionRenewal of a National Framework (NP783)to cover a full range of Chilled Goods Products.
The framework shall be for 4 years with no extension options
CPV: Dairy products
How this framework works
From the published notice- Places
- up to 3 suppliers · 3 bids received (1.0 per place) · 3 appointed (full)
- Electronic auction
- yes
The lotProcurement structure
single lot · value publishedLot #1A range of Chilled Goods products to be use by health boards across Scotland Multi…AwardedPublished value£18,500,000
A range of Chilled Goods products to be use by health boards across Scotland Multi supplier Framework unranked. The Framework Agreement may be used by all mainland and island NHS Scotland Health Boards and Special Boards
(including the Common Services Agency) and by all entities constituted pursuant to the National Health Service (Scotland) Act 1978 (i.e.
all NHS Scotland Health Boards, Special Health Boards and the Authority or other NHS organisations established pursuant to the NHS
(Scotland) Act 1978) and any Integrated Joint Boards established pursuant to the new Public Bodies (Joint Working) Scotland Act 2014.
All Scottish Hospices. Additional information: Total value shown is the estimated value for duration of the framework
The framework period shall be 4 years
What it takes to wini
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Evaluation split and conditions of participation as published; the tender pack may add morei
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Published sub-criteria (2)
- Service: 20%
- Price: 80%
Published award criteria (2)
- Service: 20
- Price: 80
- Economic & financial standing
See contract/tender documentation which incorporates requirements of the SPD
(Scotland) and the financial period for reporting is the previous 3 financial years
- Staff
- Names and qualifications of delivery staff must be submitted
- Price carries 80 of 100 points: a 10% discount moves about 8 points. This one is won on the number: sharpen the price before polishing the prose.
- “Chilled Goods” is a framework: the contest is a place on its panel, up to 3 suppliers, not a single contract.
Price arithmetic assumes straight proportional scoring; the tender pack may use another formula.
Procedure terms & legal framework
From the official record · publisher note attached- Procedure method
- Open procedure
- Legal basis
- CELEX · 32014L0024 Public Contracts Regulations 2015 (Directive 2014/24/EU)
- Procurement category
- Goods
- Notice status
- Awarded
- Procurement threshold
- Unspecified in notice
- Regulatory regime
- Standard
- Commercial structure
- Framework agreement
- Who may use this agreement
- Not stated in the notice; call-off rights may be limited to the establishing authority
- Competition type
- Competitive procedure
- GPA / WTO covered
- Yes (GPA)
- Recurring procurement
- No (one-off requirement)
- First published
- 5 Dec 2024, 12:02 GMT
- Last source update
- 24 Mar 2025, 13:44 GMT
- Award evaluation window
- 27 Jan 2025 – …
- Authority reference
NP783- FTS notice number
2025/S 000-010910- Classification (CPV)
- Delivery area
- Official registry OCID
ocds-h6vhtk-04c284Find a Tender
- Electronic trading
- e-invoicing allowed · electronic ordering · electronic payment
- Review procedure
The authority will notify economic operators who submitted a tender or (where no
deselection notification has previously been
made)applied to be selected to tender, of its decision to award the framework agreement
which notification will contain among other
information, a summary of the reasons why the economic operator was unsuccessful. The notification will
incorporate a ‘standstill period’ of a
minimum of 10 clear calendar days (or a minimum of 15 if the communication method used is
not electronic) between the date on which
the authority despatches the notice(s) and the date on which the authority proposes to
conclude the relevant framework agreement.
The bringing of court proceedings against the authority during the standstill period will
automatically continue the prohibition on entering
into the framework agreement until the court proceedings are determined, discontinued or
disposed of, or the court, by interim order, brings
to an end the prohibition. The remedies that may be awarded by the courts before the
framework agreement has been entered into include
the setting aside of the decision to award the framework agreement to the winning
tenderer(s). The bringing of court proceedings against
the authority after the framework agreement has been entered into will not affect the
framework agreement unless grounds for the imposition
of special penalties under the Public Contracts (Scotland) Regulations 2015 can be
established. Otherwise the remedies that may be
awarded by the courts where the framework agreement has been entered into are limited to
the award of damages. Economic operators are
entitled to write to the authority after receipt of the notification should they require further
clarification. The authority will respond within
15 days of such a written request, but it should be noted that receipt by the authority of such
request during the standstill period may not
prevent the authority from awarding the framework agreement following the expiry of the
standstill period. Economic operators should
approach the contracting authority in the first instance. However, the only formal remedy is
to apply to the courts:
An economic operator that suffers or is at risk of suffering, loss or damage attributable to a
breach of duty under the Public
Contracts(Scotland) Regulations 2015 or the Procurement Reform (Scotland) Act 2014,
may bring proceedings in the Sheriff Court or the court of session
Publisher note: The indicative total contract value shown is based on a circa 5 300 000 GBP per annum over the indicated duration (SC Ref:792437)
How it was run
Official noticeTender documents are also served through a separate tool: http://www.publictendersscotland.gov.uk/ ↗
- Appointment period ends
- 27 Jan 2025, 10:00 GMT
- Submission channel
- {"electronicSubmission","written"}
- Accepted languages
- en
- Bid validity
- 90 days from the deadline
- Bids opened
- 27 Jan 2025, 10:00 GMT
Timeline
27 Jan 2025 → 24 Mar 2025 · 3 dates- Admission / appointment period endsperiod end, not a bid countdown27 Jan 2025, 10:00 GMT
- Bids opened27 Jan 2025, 10:00 GMT
- Notice published24 Mar 2025, 13:44 GMT
Notice history
1 event · 2 releases on Find a Tender- Status changed to complete24 Mar 2025, 13:44 GMT
Commercial outcome & contract awards
Published awards, contracts and bid statistics, not a forecast1 suppliers are admitted to this framework without individual award values or dates, see the supplier list below.
Contracts
Contract 010910-2025-NP7832025-1
- Signed
- 28 Feb 2025
- Value
- £21,200,000
- Status
- active
Bid statistics published by the authority
| Bids | SME | VCSE | Valid bid range |
|---|---|---|---|
| 3bids · 3 electronic | 0 | — | — |
Contracting authority & participating public bodies
Dispute resolution & review bodies
- Court of SessionReview contact point
- Edinburgh Sheriff CourtReview body
Framework contractors & participating bidders
3 commercial parties on the notice- BFS Group Ltd T/A BidfoodFramework contractor
- Brake Bros LtdFramework contractor
- Fife Creamery LimitedFramework contractor
Official documents & specifications
Official links; attachments are not copiedNo document links were published on the notice.