Find a TenderClosed
Published 21 Oct 2021, 17:35 BST

Official UK procurement notice

EHC 1021 Hertford Theatre Growth and Legacy Project

Official notice

Authority: East Hertfordshire District Council (Local council)

WorksRestricted procedureAccelerated
Published estimate£16,500,000≈ £15m / year
Submissions closed 5 Nov 2021
Contract term 1 yr 1 moends 30 Mar 2023 · starts 8 Mar 2022

What is being bought

Published requirement description

East Hertfordshire District Council are currently seeking tenders for the Hertford Theatre Growth and Legacy Project. The tender documents can be accessed from the My Tenders area of the Supply Hertfordshire website and selecting the View Details button of this project. Please note the deadline for returns and allow sufficient time to make your return as late returns will not be permitted. Any questions relating to this tender should be made via correspondence on the website and can be addressed to the main contact as shown in the details above.

CPV: Building construction work · Construction work for art and cultural buildings · Construction work for buildings relating to artistic performances · Construction work for buildings relating to leisure, sports, culture, lodging and restaurants · Entertainment building construction work · Theatre construction work

The lotProcurement structure

single lot · value published
Lot #1The Council has a vision for Hertford Theatre to become a cultural hub for the… 1 yr 1 moPublished value£16,500,000

The Council has a vision for Hertford Theatre to become a cultural hub for the District and to maximise its location alongside the River Lea. To facilitate this vision a physical redevelopment of the building and the creation of new cultural and event space is proposed. In July 2018, the Council approved a capital investment of £13.5m for the Growth and Legacy option to develop and expand the Theatre. Following the development of a more detailed Feasibility Report and costs, the Council approved a further budgetary uplift to £20m in November 2019. The detailed scope of development comprises the following: Redevelopment and extension of front of house spaces to include 3 cinema screens with a minimum total capacity of 200 seats. Enhanced Main Auditorium with a capacity of 550 seats with an additional high-level balcony and new fixed seating layout to improve customer theatre experience and ensure consistency across all auditoria. The auditorium will continue to also show film. A flexible studio theatre space with around 150 seats. Film will also be shown in this space. Two hireable spaces, with one as a dance studio. Reconfigured entrance foyer. Relocated and enhanced food and beverage offer alongside and over-looking the River Lea. Acoustic improvements to the main Auditorium. Reconfigured office and backstage spaces. Improved accessibility in-line with the Equality Act including new back-stage door with accessible ramps leading to accessible changing and rehearsal spaces enabling disabled performers and participants to engage fully with the theatre and its output. Improved access and sightlines of Castle Gates by addressing access and parking concerns creating a greatly improved public realm around the entire theatre site. The project will provide an opportunity to improve the connectivity between the town, Theatre and park, opening up sightlines along the River Lea and encouraging more people to engage with these currently under-utilised areas. The project will develop a scope for partnering with the Town Council, schools and other centres of education to release the heritage story of the Motte, Castle Gardens and Hertford.

Contract period: 8 Mar 2022 – 30 Mar 2023 (1 yr 1 mo)
Delivery: East of England · Hertford, Hertfordshire
Second stage: up to 5 candidates invited to tenderVariant bids: not allowed

Procedure terms & legal framework

From the official record · publisher note attached
Procedure method
Restricted procedure
Legal basis
CELEX · 32014L0024 Public Contracts Regulations 2015 (Directive 2014/24/EU)
Procurement category
Works
Notice status
Closed
Procurement threshold
Unspecified in notice
Regulatory regime
Standard
Commercial structure
Stand-alone contract (no framework)
Competition type
Competitive procedure
GPA / WTO covered
Yes (GPA)
Recurring procurement
No (one-off requirement)
First published
21 Oct 2021, 17:35 BST
Last source update
22 Oct 2021, 12:29 BST
Authority reference
2021/S 000-026458
FTS notice number
2021/S 000-026516
Accelerated

There is a state of urgency for this procurement following two previous PCR 2015 compliant procurement processes through which the contracting authority was unable to award a contract.

Classification (CPV)
Building construction workConstruction work for art and cultural buildingsConstruction work for buildings relating to artistic performancesConstruction work for buildings relating to leisure, sports, culture, lodging and restaurantsEntertainment building construction workTheatre construction work
Delivery area
East of England (UKH23)
Official registry OCID
ocds-h6vhtk-02eec7 Find a Tender
Review and risk notes
Review procedure

The authority will incorporate a minimum 10 calendar days standstill period at the point information on the award of the contract is communicated to tenderers. Applicants who are unsuccessful shall be informed by the authority as soon as possible after the decision has been made as to the reasons why the applicant was unsuccessful. If any clarification regarding the award of the contract has not been successfully resolved, the Public Contracts Regulations 2015 (SI 2015 No 102) provide for aggrieved parties who have been harmed or are at risk of harm by breach of the rules to take legal action. Any such action must be brought within the applicable limitation period. Where a contract has not been entered into, the Court may order the setting aside of the award decision or order the authority to amend any document and may award damages. If a contract has been entered into the Court may, depending on the circumstances, award damages, make a declaration of ineffectiveness, order the authority to pay a fine, and/or order that the duration of the contract be shortened. The purpose of the standstill period referred to above is to allow the parties to apply to the Courts to set aside the award decision before the contract is entered into.

Publisher note: To access this procurement opportunity please visit www.supplyhertfordshire.uk and follow the on-screen guidance. In accordance with Regulation 53 of the Public Contracts Regulations 2015, the Council's procurement documents are available within the e-Tendering system. This procurement process is a two stage process and you will only be invited to tender if you have been successful and shortlisted from the first stage, i.e. pre-qualification. If you wish to be considered you must complete and submit a completed selection questionnaire by the specified closing date and time. Submissions cannot be uploaded after this return deadline. If you are experiencing problems In-Tend they offer a help section which includes a dedicated UK support desk which can be contacted via email: support@in-tend.com or telephone: +44 1144070065 for any website/technical questions, Monday to Friday, 8.30-17.30. The Council reserves the right at any time to cease the procurement process and not award a contract or to award only part of the opportunity described in this notice. If the Council takes up this right, then they will not be responsible for or pay the expenses or losses, which may be incurred by any organisation or tenderer as a result. The Council undertakes to hold confidential any information provided in the proposal submitted, subject to the Council's obligations under the law including the Freedom of Information Act 2000. If the organisation considers that any of the information submitted in the proposal should not be disclosed because of its sensitivity then this should be stated with the reason for considering it sensitive. The Council will then endeavour to consult with the applicant about such sensitive information when considering any request received under the Freedom of Information Act 2000 before replying to such a request.

How it was run

Official notice
Run through: portal not identified
Language: EN
Submission deadline
5 Nov 2021, 12:00 GMT
Submission channel
{"electronicSubmission","written"}
Accepted languages
en
Bid validity
180 days from the deadline
Detailed submission instructions & authority contactsFrom official release

Timeline

22 Oct 2021 → 8 Mar 2022 · 4 dates
  1. Notice published
    22 Oct 2021, 12:29 BST
  2. Submission deadline
    5 Nov 2021, 12:00 GMT
  3. Invitations to tender expected
    18 Nov 2021
  4. Contract starts
    8 Mar 2022

Notice history

2 releases on Find a Tender
Published amendments (1 · 0 deadline changes)
WhenWhatBeforeAfterShift
—TextDuration of the contract, framework agreement or dynamic purchasing system. · II.2.7End date 30 March 2023End date 31 August 2023

1 amendment published without a description.

Contracting authority & participating public bodies

East Hertfordshire District Council

Contracting authorityLocal CouncilRegional or local authorityGeneral public services Wallfields, Pegs Lane,, Hertford, East of England, SG13 8EQContact name, email, phone Published organisation website ↗

Dispute resolution & review bodies

  • High Court England and WalesReview body London
  • The High Court England and WalesMediation body London

Official documents & specifications (2)

Official links; attachments are not copied

Tender pack and attachments

  • Economic and financial selection criteriatenderEconomic and financial selection criteria
  • Technical selection criteriatenderTechnical selection criteria