Official UK procurement notice
Procurement of Contractor(s) to design and build new gas-compression asset project(s) at National Gas Transmission sites: (LOT1) Wormington Compressor Site; (LOT2) St Fergus Terminal
Authority: NATIONAL GAS TRANSMISSION PLC
What is being bought2 lots · detail below
Published requirement descriptionFollowing the RIIO-2 Re-opener mechanism submitted to Ofgem and their subsequent Compressor Emissions Final Option Selection, National Gas Transmission (NGT) intends to invite suitable Economic Operators to pre-qualify and tender for the delivery of new compressor installation projects at high-pressure gas compression sites. The procurements relate to two UK locations, Wormington Compressor Site and St Fergus Terminal to ensure compliance with MCPD legislation (Medium Combustion Plant Directive) by 2030. The purpose of this PIN is to alert the market of National Gas Transmission's intention to formally commence procurement using lots (one for each location), subject to the further issue of a Contract Notice under UCR (2016).
CPV: Construction work for the oil and gas industry
Lots and requirements (2)Procurement structure
2 lots · no lot values publishedLot #1WormingtonPlanned
National Gas Transmission (NGT) intends to invite interest from suitable Economic Operators to pre-qualify and tender for the delivery of new compressor installation at high-pressure gas compression sites. The procurement relates to new compressor installation required at Wormington Compressor Site to ensure compliance with MCPD legislation (Medium Combustion Plant Directive) by 2030. The procurement will consist of a pre-qualification of Applicants, shortlisting those to be invited to tender for lots and then a competitive tender of those shortlisted for each lot. The future works will include but not be limited to; early feasibility design, detailed design, engineering procurement, construction and commissioning of *1 new compressor unit at Wormington. New compressor train equipment will be procured separately by National Gas Transmission and free-issued to the installation contractors procured via this procurement event. Following the completion of the tender evaluation period, Contracts will be awarded for the Works (Design-and-Build) to the successful Contractor(s) LOT 1 for Wormington. Additional information: *National Gas Transmission reserve the right to include an additional new compressor train in the scope of Wormington Compressor Site - increasing the requirement from one new unit to two new units at Wormington. This is predicated on further development and agreement from National Gas Transmission and the Energy Regulator (Ofgem). Economic Operators who participate in the procurement and successfully pre-qualify for the future contract works at Wormington will also be deemed to have pre-qualified to be invited to tender for the additional (second) unit works if National Gas Transmission and Ofgem agree to progress that additional scope in the future as part of these works at Wormington.
Lot #2St FergusPlanned
National Gas Transmission (NGT) intends to invite interest from suitable Economic Operators to pre-qualify and tender for the delivery of new compressor installation at high-pressure gas compression sites. The procurement relates to new compressor installation required at St Fergus Terminal to ensure compliance with MCPD legislation (Medium Combustion Plant Directive) by 2030. The procurement will consist of a pre-qualification of Applicants, shortlisting those to be invited to tender for lots and then a competitive tender of those shortlisted for each lot. The future works will include but not be limited to; early feasibility design, detailed design, engineering procurement, construction and commissioning of 3 new compressor unit(s) at St Fergus. New compressor train equipment will be procured separately by National Gas Transmission and free-issued to the installation contractors procured via this procurement event. Following the completion of the tender evaluation period, Contracts will be awarded for the Works (Design-and-Build) to the successful Contractor for LOT 2 St Fergus.
What it takes to wini
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Evaluation split and conditions of participation as published; the tender pack may add morei
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Procedure terms & legal framework
From the official record · publisher note attached- Legal basis
- CELEX · 32014L0025 Utilities Contracts Regulations 2016 (Directive 2014/25/EU)
- Procurement category
- Works
- Notice status
- Past planning notice
- Procurement threshold
- Unspecified in notice
- Regulatory regime
- Standard
- Commercial structure
- Stand-alone contract (no framework)
- Competition type
- Competitive procedure
- GPA / WTO covered
- Unspecified in notice
- Recurring procurement
- Unspecified in notice
- First published
- 2 Apr 2024, 13:07 BST
- Last source update
- 2 Apr 2024, 13:07 BST
- Authority reference
45255000- FTS notice number
2024/S 000-010562- Classification (CPV)
- Delivery area
- Official registry OCID
ocds-h6vhtk-044ed0Find a Tender
Publisher note: Information on Ofgem's Wormington Compressor Emissions - Final Preferred Option can be found at the following link: https://www.ofgem.gov.uk/sites/default/files/2023-03/Decision - Wormington Compressor Emissions Final Preferred Option.pdf Information on Ofgem's St Fergus Compressor Emissions - Final Preferred Option can be found at the following link: https://www.ofgem.gov.uk/sites/default/files/2023-11/Decision - St Fergus Compressor Emissions Final Preferred Option.pdf Pre-qualification documents and participation will be provided using Achilles (achilles.com) so a current registration is advised.
How it was run
Official notice- Submission deadline
- —
- Accepted languages
- en
Timeline
2 Apr 2024 → 22 Apr 2024 · 2 dates- Notice published2 Apr 2024, 13:07 BST
- Tender notice expected22 Apr 2024, 00:00 BST
Commercial outcome & contract awards
Pipeline notice- Awards (0)
- No award published
- Contracts (0)
- No contract published
- Bid statistics
- No aggregate bid statistics published
Contracting authority & participating public bodies
Official documents & specifications