A457 Dudley Road Improvement Scheme Update

Official notice

Authority: Birmingham City Council (Local council)

Works
Awarded value£37,102,000published contract · exc. VAT
Awarded 21 Oct 2019
Awarded to McPhillips (Wellington) Limited

What is being bought

Published requirement description

The design and construction of a large capital improvement scheme to the A457 Dudley Road which is made up of; Heath Street, Dudley Road, Spring Hill and junctions/ side roads.

CPV: Road construction works

The lotProcurement structure

single lot · no lot value published
Lot #1To deliver the A457 Dudley Road scheme

To deliver the A457 Dudley Road scheme.

The Council's aspirations and objectives for the scheme remain unchanged and focus on improving journey times, reducing congestion, and enhancing public transport and active modes along the corridor. Improved journeys for a variety of modes will also improve the attractiveness of the area, stimulating economic

growth through enabling access to key development sites which will help to bring forward approximately 3,000 new homes along with other local facilities and employment opportunities. This in turn will support and protect the city's growth objectives within the Greater Icknield area.

In addition, the A457 Scheme provides improvements for public transport, pedestrians and cyclists to align with the Emergency Transport Plan and Active Travel Plan introduced following Covid-19 and aspires towards the longer-term priorities of the Council in terms of sustainable transport and working towards net zero carbon by 2030.

Delivery: UK

Procedure terms & legal framework

From the official record
Legal basis
CELEX · 32014L0024 Public Contracts Regulations 2015 (Directive 2014/24/EU)
Procurement category
Works
Notice status
Awarded
Procurement threshold
Unspecified in notice
Regulatory regime
Standard
Commercial structure
Stand-alone contract (no framework)
Competition type
Competitive procedure
GPA / WTO covered
Unspecified in notice
Recurring procurement
Unspecified in notice
First published
15 Nov 2023, 22:40 GMT
Last source update
3 Oct 2024, 17:05 BST
FTS notice number
2024/S 000-031786
Classification (CPV)
Road construction works
Delivery area
UKWest Midlands (UKG)
Official registry OCID
ocds-h6vhtk-041a3e Find a Tender

Notice history

2 releases on Find a Tender
Published amendments (1 · 0 deadline changes)
WhenWhatBeforeAfterShift
—TextV.2.4Total value of the procurement: £37,102,000Total value of the procurement: £22,870,000

1 amendment published without a description.

Commercial outcome & contract awards

Published awards, contracts and bid statistics, not a forecast
Awards 1
Awarded value £37,102,0001 contract exc. VAT
Contracts signed 1latest 21 Oct 2019
Awarded toValueDateStatus
McPhillips (Wellington) Limited£37,102,000 †—Awarded

Contracts

  • Contract 033857-2023-A457-1 · McPhillips (Wellington) Limited

    Signed
    21 Oct 2019
    Value
    £37,102,000
    Status
    active
    • Change The proposed contract modification for additional works have become necessary the design changes as a result of new government policies regarding sustainable transport; the latest LTN 1/20 design guidance which came into operation during the contract period; the imposed time constraints from the funding conditions. As a consequence, Phases 5 and 6 are required to be completed incorporating a modification to the existing contract. The Council is seeking to undertake these in accordance with PCR 2015 Regulation 72(b)(ii) where a change of contractor 'would cause significant inconvenience or substantial duplication of costs for the contracting authority' This increase would cause the contract value to exceed the 50% tolerance. However, the Council will publish a notice in accordance with PCR 2015, Regulation 72(3) and as a further mitigation of additional cost increases will separately tender Phase 7., Need for additional works, services or supplies by the original contractor/concessionaire: The proposed contract modification for additional works have become necessary the design changes as a result of new government policies regarding sustainable transport; the latest LTN 1/20 design guidance which came into operation during the contract period; the imposed time constraints from the funding conditions. As a consequence, Phases 5 and 6 are required to be completed incorporating a modification to the existing contract.

Contracting authority & participating public bodies

BIRMINGHAM CITY COUNCIL

Contracting authorityLocal Council BIRMINGHAM, West Midlands, B4 7WBContact email

Dispute resolution & review bodies

  • High Court of JusticeReview body London

Bidders & participating suppliers

1 commercial party on the notice

Official documents & specifications

Official links; attachments are not copied

No document links were published on the notice.