Official UK procurement notice
Commercial Heating and Ventilation contract extension Contract
Authority: Dacorum Borough Council (Local council)
What is being bought
Published requirement descriptionOn June 30, 2015, Dacorum Borough Council ("Dacorum") entered a contract for an initial period of five-years with Orion Building Engineering Services Limited ("OBES") for Commercial Heating and Ventilation services (the "Contract"). The Contract included annual extensions up to ten years, contingent on supplier performance.
The Contract entails maintaining and installing commercial heating and ventilation systems for properties under the responsibility of Dacorum. It includes routine maintenance and repairs for council properties including residential buildings and corporate assets.
This Voluntary Ex-Ante Transparency Notice (VEAT) relates to a proposed extension of the Contract for a further nine (9) months with a longstop date of March 31, 2026, to allow Dacorum to conduct a re-procurement exercise for the long-term successor to the Contract.
CPV: Repair and maintenance services of central heating
The lotProcurement structure
single lot · no lot value publishedLot #1Dacorum plans to extend the term of the Contract with OBES for a bridging period of…
Dacorum plans to extend the term of the Contract with OBES for a bridging period of nine months to conduct a re-procurement exercise for the long-term successor to the Contract. The extension will allow Dacorum sufficient time to run a market-engagement, commissioning and re-procurement process, with the new service to start by April 1, 2026.
Procedure terms & legal framework
From the official record- Procedure method
- Negotiated without publication of a contract notice
- Legal basis
- CELEX · 32014L0024 Public Contracts Regulations 2015 (Directive 2014/24/EU)
- Procurement category
- Services
- Notice status
- Awarded
- Procurement threshold
- Unspecified in notice
- Regulatory regime
- Standard
- Commercial structure
- Stand-alone contract (no framework)
- Competition type
- Competitive procedure
- GPA / WTO covered
- Yes (GPA)
- Recurring procurement
- Unspecified in notice
- First published
- 12 Jun 2025, 14:27 BST
- Last source update
- 12 Jun 2025, 14:27 BST
- FTS notice number
2025/S 000-031966- Classification (CPV)
- Delivery area
- Official registry OCID
ocds-h6vhtk-0547c5Find a Tender
- Why no open competition
New works/services, constituting a repetition of existing works/services and ordered in accordance with the strict conditions stated in the directive
- Published justification
Award of a contract without prior publication of a call for competition in the cases listed below:
- The procurement falls outside the scope of application of the directive.
The existing Contract with OBES commenced on June 30, 2015 and expires on June 30, 2025. Dacorum intends to extend the Contract by nine (9) months, with provision to terminate earlier, to allow Dacorum time to run a comprehensive re-procurement exercise for the appointment of a long-term successor to the Contract.
Dacorum's position is that the proposed extension is not a permitted modification under Regulation 72(1)(e) of the Public Contract Regulations 2015 (as amended) ("PCR") (non-substantial modifications) and that none of the conditions set out in Regulation 72(8) are met.
With reference to Regulation 72(8)(a), the proposed modification will not render the Contract materially different in character from the one initially concluded as there will be no change to the services or works to provide for the extension period (either in terms of the nature of the works/services or the quantity). The modification is an extension of term only.
With reference to Regulation 72(8)(b), Dacorum does not consider that the modification introduces conditions which, had they been part of the initial procurement procedure, would have- (i) allowed for the admission of other candidates than those initially selected, (ii) allowed for the acceptance of a tender other than that originally accepted, or (iii) attracted additional participants in the procurement procedure. The only effect of the modification is to extend the term of the Contract and so Dacorum does not consider that there would have been any change to the outcome of the original procurement.
With reference to Regulation 72(8)(c), the modification will not change any of the terms of the Contract other than the term, and so there will be no change to the economic balance of the contract.
Dacorum does not consider that the modification will extend the scope of the Contract considerably within the meaning of Regulation 72(8)(d) in the context of the Contract as a whole (10 years). No change is proposed to the nature or quantity of the works and services and no new services or works will be included in the scope. The period of the extension may be reduced if the procurement exercise is completed before the end of the extension period.
Regulation 72(8)(e) of the PCR is not engaged as there is no change to the contractor.
The purpose of the modification is to provide a 'bridging period' to conduct a comprehensive re-procurement exercise for the long-term successor to the Contract. The modification will therefore allow continuity of service and value for money for Dacorum while it conducts this exercise, the scope of which will include market testing, assessment of risks and uncertainty within the construction and housing repair sector, corresponding development and design of procurement strategy, managing the orderly wind-down and exit of the Contract with the existing supplier and mobilisation of the new contract.
- Review procedure
In accordance with Regulation 88 to Regulation 102 of the PCR 2015 (particularly, Regulations 92, 93, 94 and 99 in relation to deadlines).
Commercial outcome & contract awards
Published awards, contracts and bid statistics, not a forecast| Awarded to | Value | Date | Status |
|---|---|---|---|
| Orion Building Engineering Services LtdSME | £180,000 † | — | Awarded |
Contracts
Contract 031966-2025-1 · Orion Building Engineering Services LtdSME
- Signed
- 11 Jun 2025
- Value
- £180,000
- Status
- active
Contracting authority & participating public bodies
Dispute resolution & review bodies
- High Court of England and WalesReview body
Bidders & participating suppliers
1 commercial party on the notice- Orion Building Engineering Services LimitedAwarded supplier
Official documents & specifications
Official links; attachments are not copiedNo document links were published on the notice.