Delivery of pre-construction services in relation to the delivery of Phase 1 of the development at Victory Quay (Tipner East)

Official notice

Authority: VIVID Housing Ltd (Charity / VCSE)

Direct award
Awarded value£1,600,000published award · exc. VAT
Awarded 24 Apr 2025no call for competition
Awarded to P.M.C. CONSTRUCTION AND DEVELOPMENT SERVICES LIMITED

What is being bought

Published requirement description

VIVID is proposing to develop the site at Victory Quay (Tipner East) by reference to a number of phases. This Contract Award Notice relates to the award of a Pre-Construction Services Agreement ("PCSA") in respect of Phase 1. The services covered by the PCSA include S278 / S38 design and submission, sub-structure and superstructure design review and evolution for design freeze, select planning condition discharges and amendments, drainage design review and finalisation, conclusion of Bird Conservation Area design and sign-off, SAP Modelling, Future Homes standard review & SBEM modelling, fire safety design review, hard and soft landscaping design, and liaison with Building Control, LPA & Highways.

This Contract Award Notice sets out VIVID's intention to enter into a bespoke PCSA with PMC leading into the award of a JCT Design & Build Contract for the delivery of the infrastructure works and the Phase 1 works (subject to satisfactory performance under the PCSA, meeting pre-conditions set out in the PCSA, and subject to VIVID obtaining the necessary internal approvals). This Contract Award Notice is published in VIVID's name, although it may be VIVID or Vestal Development Limited (group company) who subsequently enters into the PCSA and any ensuing JCT with PMC, and this notice is therefore advertised for the benefit of both VIVID and Vestal.

The anticipated value of the PCSA to be awarded to PMC is in the region of £1.2 million to £1.6 million (ex VAT), with the overall anticipated value for the delivery of Phase 1 being in the region of £50 to 60 million (ex VAT).

The works to be delivered under the JCT D&B Contract for Phase 1 include the delivery of 181 homes plus the core main road layout, ground raising, spine road, sea wall coastal path, primary service to site, drainage & foul water pumping station, landscaping, bird conservation area, temporary and permanent boundaries and a commercial space for marketing and management. VIVID will publish a further Transparency Notice in due course ahead of awarding the JCT D&B Contract (subject to the pre-conditions and internal approvals noted above).

The lotProcurement structure

single lot · no lot value published

Procedure terms & legal framework

From the official record
Procedure method
Direct award
Legal basis
UKPGA · 2023/54 Procurement Act 2023
Notice status
Awarded without competition
Procurement threshold
Unspecified in notice
Regulatory regime
Standard
Commercial structure
Stand-alone contract (no framework)
Competition type
Direct award (no call for competition)
GPA / WTO covered
Unspecified in notice
Recurring procurement
Unspecified in notice
First published
24 Apr 2025, 13:59 BST
Last source update
17 Jun 2025, 13:32 BST
FTS notice number
2025/S 000-032951
Latest notice
Contract details notice (UK7)
Delivery area
South East (UKJ)
Official registry OCID
ocds-h6vhtk-0506fe Find a Tender
Why no open competition
Single Suppliers Technical Reasons
Published justification

The award of the contract is permitted in accordance with section 41 and paragraph 6 of Schedule 5 to the Procurement Act 2023 on the basis that:

(a) Due to an absence of competition for technical reasons, only PMC is able to deliver the pre-construction services under the PCSA; and

(b) There is no reasonable alternative for the delivery of the Phase 1 works.

Under an earlier PCSA, local contractor PMC completed complex and technical whole site remediation & capping works. Followed by a 500-meter sea wall which is due to be completed by September 2025. The PCSA also included PMC entering detailed negotiations with the LPA, The Marine Management Organization, Environment Agency and Natural England to obtain a FRAP and MMO Licence for work on the shore of Tipner Lake a SSSI & RAMSAR. These licenses are in PMC's name and restrict operations between April and November due to over wintering birds.

Of particular note:

  1. PMC has specific know-how (in relation to the site and works already delivered) that is essential to the effective delivery of the pre-construction services, infrastructure works and Phase 1 works (and the continued success of the overall build programme for the site as a whole) which would be prohibitively timely and expensive for another contractor to acquire and, as such, would be an unreasonable alternative for the pre-construction services;
  2. Phase 1 is required to be compatible with ongoing infrastructure works that are already being provided by PMC under separate contracts (particularly in relation to the sea wall and the drainage infrastructure works that will be required for Phase1 and the future phases) and there are therefore technical interoperability requirements which necessitate a direct award to PMC;
  3. The site adjoins the Tipner intertidal lake which is included within national and international nature conservation designations (Portsmouth Harbour Site of Special Scientific Interest (SSSI), Portsmouth Harbour Special Protection Area (SPA), Dorset and Solent Coast SPA and Portsmouth Harbour Ramsar Site) and areas containing ecological interest. It is in an extremely ecologically and environmentally sensitive location and is monitored by all the relevant ecological agencies. When combined with a historical contamination legacy, it requires a detailed understanding and construction methodology to deliver and to avoid biodiversity conflict. This is particularly relevant to subterranean ground works and works alongside the foreshore, to minimize the risk to the immediately adjoining tidal lake ecology, the chalk aquifers, wading & over wintering birds, and biodiversity within the mud flats including a Protected Bass nursery area.
  4. VIVID is in receipt of Homes England grant funding that requires the infrastructure works and key Phase 1 works to be completed by March 2027. Due to timing constraints imposed by this funding, VIVID requires a contractor with specific knowledge of the site and the operational requirements for Phase 1. Given PMC's prior involvement in delivering substantially similar works on the site (including PMC's technical knowledge and specific know-how in relation to the site), PMC is uniquely placed to deliver the Phase 1 design services and works as a result of the initial enabling works that have already been carried out by PMC on-site.

Given the above, VIVID considers that PMC is uniquely placed to deliver the pre-construction services for Phase 1 on the basis that there is an absence of competition for technical reasons, and that there is no reasonable alternative to PMC delivering key services and works within the required timescales.

Whilst the relevant services and works are delivered under Phase 1, VIVID will be commencing a regulated procurement exercise in accordance with the competitive flexible procedure under the Procurement Act 2023 for the delivery of the remaining phases.

How it was run

Official notice
Submission deadline
—

Timeline

6 May 2025 → 17 Jun 2025 · 2 dates
  1. Standstill ends
    6 May 2025, 23:59 BST
  2. Notice published
    17 Jun 2025, 13:32 BST

Notice history

4 events · 3 releases on Find a Tender · since 24 Apr 2025
  1. Transparency notice published
    24 Apr 2025, 13:59 BST
    UK5
  2. Contract award notice published
    24 Apr 2025, 14:02 BST
    UK6
  3. Contract signature expected
    7 May 2025, 23:59 BST
    scheduled
  4. Contract details notice published
    17 Jun 2025, 13:32 BST
    UK7

Commercial outcome & contract awards

Published awards, contracts and bid statistics, not a forecast
Awards 1
Awarded value £1,600,0001 award exc. VAT
Contracts signed 1latest 19 May 2025
Awarded toValueDateStatus
P.M.C. CONSTRUCTION AND DEVELOPMENT SERVICES LIMITED7 May 2025 – 31 Oct 2025 · up to 31 Dec 2025Extensions: The PCSA may need to be extended to cover additional design work to achieve Phase 1 build cost certainty£1,600,00024 Apr 2025Awarded

Contracts

  • Delivery of pre-construction services in relation to the delivery of Phase 1 of the development at Victory Quay (Tipner East) · P.M.C. CONSTRUCTION AND DEVELOPMENT SERVICES LIMITED

    Signed
    19 May 2025
    Value
    £1,600,000
    Period
    20 May 2025 – 31 Oct 2025 · up to 31 Dec 2025 with extensions
    Status
    active
    Extensions
    The PCSA may need to be extended to cover additional design work to achieve Phase 1 build cost certainty

    No agreed KPIs: Due to the relatively short term and programme led nature of this contract, KPIs are not required to monitor and manage successful delivery. There is a Key Date Schedule appended to the contract that details when specific elements of the design work are to be completed

Contracting authority & participating public bodies

VIVID Housing Ltd

Contracting authorityPublic authority - sub-central government GB-MPR: 7544 · GB-PPON: PNYP-8277-DWPP Peninsular House, Wharf Road, Portsmouth, South East, PO2 8HBContact email

Bidders & participating suppliers

1 commercial party on the notice

Official documents & specifications (3)

Official links; attachments are not copied

Notices published for this procedure

  • Contract details notice contractContract details noticeUK7Contract details notice on Find a Tender
  • Contract award notice awardContract award noticeUK6Contract award notice on Find a Tender
  • Transparency notice awardTransparency noticeUK5Transparency notice on Find a Tender