Find a TenderAwarded without competition
Published 7 Mar 2022, 11:17 GMT

Official UK procurement notice

Development at Elwick Place, Ashford, Kent

Official notice

Authority: Ashford Borough Council (Local council)

WorksAward procedure without prior publication of a call for competition
Awarded value£80,250,000published contract · exc. VAT
Awarded 4 Mar 2022no call for competition
Awarded to Stanhope PLC

What is being bought

Published requirement description

A development agreement (“DA”) was originally entered into in 2010 between the South East England Development Agency (“SEEDA”) and Stanhope PLC and concerned the re-development, in phases, of a site in the centre of Ashford known as Elwick Place according to a masterplan to be agreed between the parties. In 2015 the Council acquired the site and the rights and obligations formerly vested in SEEDA under the DA. The Phases are now as follows: Phase 1 (cinema, hotel, restaurants, retail units and car park), Phase 2 (200 residential flats) and Phase 3 (yet to be agreed). The parties have now agreed certain changes to the DA. This notice concerns those changes.

CPV: Construction work for buildings relating to leisure, sports, culture, lodging and restaurants · Multi-dwelling buildings construction work

The lotProcurement structure

single lot · no lot value published
Lot #1Phase 1 of the development has now been completedAwarded

Phase 1 of the development has now been completed. The DA required Stanhope to begin the process of drawing down Phase 2 prior to two key dates: the “Long Stop Date” (16 March 2022) and the “Phase Termination Date” (4 May 2022) but it may only do so after satisfying a number of conditions. Delays caused by (a) the Covid-19 pandemic; and (b) the Stodmarsh issue (see below) each independently and also together cumulatively mean that Stanhope will not be able to meet the conditions before the deadlines.

The Stodmarsh issue arises from formal statutory advice issued by Natural England in 2020 on development proposals in the Stour Valley River Catchment Area ( “SVRCA”) and the potential for these to increase harmful nutrient impacts at designated protected lakes at Stodmarsh in east Kent. The SVRCA covers large parts of Ashford Borough including Elwick Place. Planning applications for housing development within the SVRCA cannot now be determined until formal assessment of the effects on the Stodmarsh Lakes has been completed by the Council as planning authority. The Council is progressing a strategy to offer suitable mitigations for sites (such as Elwick Phase 2) not able to offer onsite mitigation, but timescales for this are uncertain so it is unclear when the planning authority will be able to grant a Phase 2 planning permission on terms that will enable the drawdown conditions to be satisfied. Accordingly, the parties entered into an agreement on 4 March 2022 to extend each of the deadlines (the “Extension”) by up to 515 days or (if later) until 40 days after (i) any off-site Stodmarsh mitigation measures required of the developer in respect of Phase 2 have been complied with or if later (ii) the period for any Judicial Review challenge to the Phase 2 planning permission has expired with no challenge being made or any challenge has been resolved. Provided that if Stanhope has yet to complete a planning obligation that would result in the issue of a Phase 2 planning permission the maximum Extension is 9 months from the date on which the local Council’s resolution to grant a Phase 2 planning permission will not require any offsite Stodmarsh mitigation measures to be complied with by Stanhope. The aim is to restore Stanhope, in terms of the timing of Phase 2, to the situation it would have been in had Covid and Stodmarsh not intervened. The parties have also provided for new activity milestones in respect of Phase 2. If Stanhope fails to achieve any of these milestones the Council may terminate the DA. Additionally, Stanhope has agreed to relinquish certain rights it had over the Phase 3 land. Additional information: The current value of the Development Agreement as provided in this notice strips out the effects of inflation, as required by Regulation 72(7) Public Contracts Regulations 2015

Delivery: South East · Ashford, Kent

Procedure terms & legal framework

From the official record · publisher note attached
Procedure method
Award procedure without prior publication of a call for competition
Legal basis
CELEX · 32014L0024 Public Contracts Regulations 2015 (Directive 2014/24/EU)
Procurement category
Works
Notice status
Awarded without competition
Procurement threshold
Unspecified in notice
Regulatory regime
Standard
Commercial structure
Stand-alone contract (no framework)
Competition type
Direct award (no call for competition)
GPA / WTO covered
Yes (GPA)
Recurring procurement
Unspecified in notice
First published
7 Mar 2022, 11:17 GMT
Last source update
7 Mar 2022, 11:17 GMT
FTS notice number
2022/S 000-006141
Classification (CPV)
Construction work for buildings relating to leisure, sports, culture, lodging and restaurantsMulti-dwelling buildings construction work
Delivery area
South East (UKJ4)
Official registry OCID
ocds-h6vhtk-031e96 Find a Tender
Why no open competition
The procurement falls outside the scope of application of the directive
Published justification

Regulation 72(1)(c) Public Contracts Regulations 2015 applies. Stanhope planned to seek bids from residential development and funding partners in Spring 2020, in ample time to satisfy the drawdown conditions for Phase 2 within the terms of the DA. The March 2020 Covid national lockdown and the ongoing restrictions thereafter radically altered the situation causing huge uncertainties for valuation, funding and development generally. Funders were preoccupied with preserving their existing investments through the unprecedented crisis: there was no appetite for taking on new projects. Accordingly, Stanhope was advised not to engage the market as planned. Only in late Spring 2021 was Stanhope able to progress the appointment of partners and the process of satisfying the drawdown conditions, which nonetheless cannot be completed until the Stodmarsh situation has been resolved. Neither the Covid-19 pandemic, and the resulting series of national lockdowns and regional tiered restrictions on normal activities, nor the Stodmarsh issue could have been foreseen by a diligent authority when the DA was entered into in 2010 and none of these events were foreseen by the Council. The new activity milestones and Stanhope’s relinquishing of certain rights over the Phase 3 land, do not entail substantial change: if they alter the economic balance at all they do so in favour of the Council. None of the amendments change the nature of the agreement.

Publisher note: The current value of the Development Agreement as provided in this notice strips out the effects of inflation, as required by Regulation 72(7) Public Contracts Regulations 2015 (MT Ref:224963)

Commercial outcome & contract awards

Published awards, contracts and bid statistics, not a forecast
Awards 1
Awarded value £80,250,0001 contract exc. VAT
Bids received 1
Contracts signed 1latest 4 Mar 2022
Awarded toValueDateStatus
Stanhope PLC£80,250,000 †—Awarded

Contracts

  • Contract 006141-2022-1 · Stanhope PLC

    Signed
    4 Mar 2022
    Value
    £80,250,000
    Status
    active

Bid statistics published by the authority

BidsSMEVCSEValid bid range
1bids · 1 electronic · 1 from abroad0——

Contracting authority & participating public bodies

Ashford Borough Council

Contracting authorityLocal CouncilRegional or local authorityGeneral public services Civic Centre, Tannery Lane, Ashford, South East, TN23 1PLContact email, phone

Dispute resolution & review bodies

  • High Court, Royal Courts of JusticeReview body London

Bidders & participating suppliers

1 commercial party on the notice

Official documents & specifications

Official links; attachments are not copied

No document links were published on the notice.