Published requirement descriptionThe Works comprises three Work Elements (WE1, WE2, WE3), as described below.
Work Element 1 (WE1): Land clearance, soil remediation and bulk excavation and backfilling of a 4.4 ha site to provide a Working Platform. Land clearance shall include removal of vegetation, surface soil bunds and any above or below-ground concrete, brick, obstructions, waste or other structures. The remediation works shall include excavation of known areas of soil contaminated by Heavy Fuel Oil (HFO), removal of the soil by road transport and treatment/ disposal at an appropriately licensed waste management facility, together with verification and validation of remedial excavations and remaining site area. The remaining area (uncontaminated soils) shall be subject to bulk excavation, including the break out and removal of surfacing, below ground obstructions and six large concrete tank bases with cropping of underlying piles. The void space resulting from soil remediation and bulk excavation shall be backfilled to a specified formation level with uncontaminated geotechnically suitable imported material to the required engineering specification to achieve a Working Platform Certificate.
Work Element 2 (WE2): Preparation of a 1.6 ha site for a temporary construction laydown area. The works shall comprise land clearance by removal of surface soil bunds, vegetation and any above-ground concrete or other structures to create a level surface, including disposal or waste arisings at an appropriately licensed waste management facility, followed by installation of a geomembrane and placement of a gravel layer above the geomembrane to provide a stable, level ground surface. If found, the works shall include excavation and removal of any unexpected contamination that may be encountered.
Work Element 3 (WE3): Preparation of a 1,250 m two-way carriageway length of an access road (on private land). The works shall comprise preparation of an existing access road for use by construction traffic associated with the Works and for future use by construction traffic during redevelopment of the Site, including road widening, bend alignments, surfacing, shoulders, cambers, surface water drainage relocation and connections to existing stormwater system. If found, the works shall include excavation and removal of any unexpected contamination encountered during the works.
The Works shall be carried out in accordance with the technical specifications and other requirements, provisions and conditions specified by the Employer in the ITT Documentation.
CPV: Site preparation work
The lotProcurement structure
single lot · no lot value publishedLot #1The Works include all design, engineering, procurement, manufacture, supply, site…
The Works include all design, engineering, procurement, manufacture, supply, site preparation, civil works, construction and/or installation required for site remediation and enabling works to prepare a construction site for a new converter station associated with a planned electricity interconnector between the UK and France. The Works comprise, inter alia:
Work Element 1 (WE1): Land clearance, soil remediation and bulk excavation and backfilling (4.4 ha site area):
Removal of ruderal vegetation within the 4.4 ha site area.
Remediation of known areas of soil contaminated by Heavy Fuel Oil (HFO) within the 4.4 ha site area by excavation to a depth of 0.5 m to 1.5 m below ground level, removal of the soil by road transport and treatment/disposal at an appropriately licensed waste management facility. The estimated quantity of contaminated soil is 8,500 m3.
Verification and validation of the removal of all contaminated material from the excavations by sampling of the base and side walls.
Verification and validation of the absence of contaminated material in remaining areas of the 4.4 ha site area by trial pits with sampling at 1 m vertical intervals.
Removal of surface soil bunds and any above or below-ground concrete, brick, obstructions, waste or other structures within the 4.4 ha site area.
Bulk excavation to a depth of 1.4 m below ground level of the remaining areas within the 4.4 ha site area and the break out and removal of surfacing, below ground obstructions and six large concrete tank bases with cropping of the underlying piles.
Backfilling of void space resulting from soil remediation and bulk excavation to ground level, including a 300 mm capping layer, with uncontaminated geotechnically suitable imported material to the required engineering specification to achieve a Working Platform Certificate.
The Works also include supplementary site management requirements, including decommissioning of existing boreholes, surface water and groundwater collection, treatment and disposal, and installation of a filter drain network within the 4.4 ha site area.
Work Element 2 (WE2): Temporary construction laydown area preparation works (1.6 ha site area):
Land clearance by removal of surface soil bunds, vegetation and any above-ground concrete or other structures within the 1.6 ha site area to create a level surface, including disposal or waste arisings at an appropriately licensed waste management facility.
Installation of a geomembrane within the 1.6 ha site area to prevent migration of any surface contamination caused by future temporary uses into the sub-surface layers, and placement of a 300 mm gravel layer above the geomembrane to provide a stable, level ground surface.
If found, excavation and removal of any unexpected contamination encountered during the works.
Work Element 3 (WE3): Access road preparation works (1,250 m two-way carriageway length):
Preparation of the 1,250 m section of the access road for use by construction traffic associated with the Works and for future use by construction traffic during redevelopment of the Site.
Surface repairs and formation repairs to a depth of 300 mm below ground level for approximately 1,000 m road section.
Road widening and bend alignments for approximately 770 m road section and surface area of 1,500 m2.
Construction of one (1 No.) junction from the access road.
If found, excavation and removal of any unexpected contamination encountered during the works.
The works include formation, surfacing, shoulders, cambers, surface water drainage relocation and connections to existing stormwater system and other measures required for the safe movement of road vehicles.
What it takes to wini
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Evaluation split and conditions of participation as published; the tender pack may add morei
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
- Legal form for consortia
- Refer to procurement documents
- Staff
- Names and qualifications of delivery staff must be submitted
- Shortlisting
- Tenderers must demonstrate that they comply with the minimum requirements listed below in order to be considered for selection: 1) Annual financial turnover for similar Works to those required under the Contract for each of the past three (3) financial years: £10 million 2) Relevant experience: Ten (10) contracts completed in the past five (5) years and five (5) reference contracts for similar Works completed in the past three (3) years 3) Tax affairs: All applicable Taxes have been duly paid and tax affairs are in order 4) Insurance cover in place or to be taken out for the Works: Construction "All Risks" (CAR) Insurance: minimum £10 million Employers Liability Insurance: minimum £10 million Public Liability and Third Party Liability: minimum £10 million Professional Indemnity: minimum £5 million
Procedure terms & legal framework
From the official record- Procedure method
- Open procedure
- Legal basis
- CELEX · 32014L0025 Utilities Contracts Regulations 2016 (Directive 2014/25/EU)
- Procurement category
- Works
- Notice status
- Closed
- Procurement threshold
- Unspecified in notice
- Regulatory regime
- Standard
- Commercial structure
- Stand-alone contract (no framework)
- Competition type
- Competitive procedure
- GPA / WTO covered
- Unspecified in notice
- Recurring procurement
- No (one-off requirement)
- First published
- 22 Apr 2021, 00:06 BST
- Last source update
- 22 Apr 2021, 00:06 BST
- Award evaluation window
- 14 Jul 2021 – …
- Authority reference
ITT-UKSITE-REM-001- FTS notice number
2021/S 000-008572- Classification (CPV)
- Delivery area
- Official registry OCID
ocds-h6vhtk-02a8edFind a Tender- Contract terms summary
Refer to procurement documents
- Performance terms
Refer to procurement documents
How it was run
Official notice- Submission deadline
- 5 May 2021, 23:59 BST
- Submission channel
- {"electronicSubmission"}
- Accepted languages
- en
- Participation fee
- document
- Bids opened
- 14 Jul 2021, 12:00 BST
- Deposits and guarantees
- Refer to procurement documents
Timeline
22 Apr 2021 → 14 Jul 2021 · 3 dates- Notice published22 Apr 2021, 00:06 BST
- Submission deadline5 May 2021, 23:59 BST
- Bids opened14 Jul 2021, 12:00 BST
Contracting authority & participating public bodies
Dispute resolution & review bodies
- To be determinedReview body
Official documents & specifications (2)
Official links; attachments are not copiedTender pack and attachments
- Economic and financial selection criteria
- Technical selection criteria