Salmesbury Waste Water Pumping System Construction
Authority: Lancashire County Council (Local council)
What is being bought
Published requirement descriptionThe project is required to provide Foul Water Drainage as part of the ongoing development works at Samlesbury Enterprise Zone. The successful contractor will be required to provide final design for the system, construction of a new foul pumping station and approximately 2,750m of rising main.
Cundall (Engineering Consultancy) have undertaken the initial design for the foul water drainage system, and this has been approved by United Utilities. The final design and construction works will be carried out in accordance with all United Utilities standards therefore the successful contractor will be required to obtain all necessary approvals for the works from United Utilities, and this will be a requirement for practical completion.
The new foul pump station will be constructed on private land, which is adjacent to Sir Frederick Page Way, however the rising main will need to be constructed in the adopted highway. The successful contractor is responsible for traffic management and gaining all necessary consents from the Highway Authority in order construct the rising main.
The final connection into the United Utilities receptor will be across United Utilities land.
On completion, the successful contractor will also be required to provide planned maintenance for an initial period of 12 months. This period may be extended by instruction from the Project Manager.
The contract is anticipated to commence in June 2026 and the term of the contract will be 8 months, with an additional twelve months minimum maintenance period. This may be extended further if the system is not adopted by United Utilities in the first twelve months. United Utilities shall adopt the site when 50% of the site is occupied.
CPV: Construction work · Installation services (except software) · Sewage pumps
The lotProcurement structure
single lot · value publishedLot #1AwardedPublished value£1,250,000
What it takes to wini
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Evaluation split and conditions of participation as published; the tender pack may add morei
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Lot awarding rule: Selection / Award Criteria to be applied The Authority will first evaluate the Common Assessment Standard (CAS) Selection Questionnaire and those bids that pass this stage will be evaluated against the criteria set out below. AWARD CRITERION WEIGHTING Stage 1 - Suitability Assessment - Common Assessment Standard (CAS) PASS / FAIL Stage 2 - Award Criteria - Quality 30% Stage 2 - Award Criteria - Price 60% Stage 2 - Award Criteria - Social Value (via the Social Value Portal using the Lancashire TOMs.) 10% TOTAL 100%
Procedure terms & legal framework
From the official record- Procedure method
- Below threshold - open competition
- Legal basis
- UKPGA · 2023/54 Procurement Act 2023
- Procurement category
- Works
- Notice status
- Cancelled
- Procurement threshold
- Below threshold
- Regulatory regime
- Standard
- Commercial structure
- Stand-alone contract (no framework)
- Competition type
- Competitive procedure
- GPA / WTO covered
- Unspecified in notice
- Recurring procurement
- Unspecified in notice
- First published
- 4 Feb 2026, 11:15 GMT
- Last source update
- 13 Aug 2026, 14:24 BST
- FTS notice number
2026/S 000-009867- Latest notice
- Procurement termination notice (UK12)
- Classification (CPV)
- Delivery area
- Official registry OCID
ocds-h6vhtk-0646adFind a Tender
How it was run
Official notice- Submission deadline
- 13 Mar 2026, 12:00 GMT
- Clarification deadline
- 27 Feb 2026, 12:00 GMT
- Submission channel
- Official e-sourcing portal
- Electronic submission
- Allowed
Timeline
4 Feb 2026 → 13 Aug 2026 · 5 dates- Tender notice published265 days ago4 Feb 2026, 11:15 GMT
- Clarification questions by242 days ago27 Feb 2026, 12:00 GMT
- Submission deadline228 days ago13 Mar 2026, 12:00 GMT
- Contract starts126 days ago24 Jun 2026, 00:00 BST
- Latest notice published75 days ago13 Aug 2026, 14:24 BST
Notice history
3 events · 2 releases on Find a Tender · since 4 Feb 2026- Tender notice published4 Feb 2026, 11:15 GMTUK4
- Procurement termination notice published13 Aug 2026, 14:24 BSTUK12
- Status changed to complete13 Aug 2026, 14:24 BST
Commercial outcome & contract awards
Published awards, contracts and bid statistics, not a forecast| Awarded to | Value | Date | Status |
|---|---|---|---|
| supplier not published | — | 13 Aug 2026 | Cancelled |
Contracting authority & participating public bodies
Official documents & specifications (4)
Official links; attachments are not copiedTender pack and attachments
Notices published for this procedure
- Procurement termination notice Procurement termination notice on Find a Tender
- Tender notice Tender notice on Find a Tender