Official UK procurement notice
Strathfoyle Greenway - Consultants PQQ T ENV 20-058
Authority: Derry City and Strabane District Council (Local council)
What is being bought
Published requirement descriptionThe Contracting Authority for the Contract is Derry City and Strabane District Council DESCRIPTION OF THE SERVICE REQUIRED The Economic Operator shall provide the following Services outlined below: PROJECT BACKGROUND The Strathfoyle – Maydown - Eglinton Greenway project is a proposed 3.7km extension to the very popular Waterside Greenway, which will link the residential area of Strathfoyle to Derry and the wider Greenway network. It also provides a commuting route to Foyle Port and Maydown. The project has been in development for a number of years which has meant various stretches of the route are at different stages of design development. Therefore it is expected that the project will be developed in 2 distinct sections. Section 1 – Strathfoyle Greenway between Foyle Bridge and Stradowen Drive, 2.7km This is a single linear route, running through a 20-25m green corridor, from below the Foyle Bridge to Stradowen Drive in Strathfoyle. Planning is currently secured for this section of the Greenway. Works would involve but not be limited to construction of a 3.5m asphalt greenway with lighting, drainage, landscaping, retaining structures, embankments, fencing, ancillary works, as well as creating links to attractions, amenities and residential areas from the greenway. Section 2 – Strathfoyle Greenway improvement to paths within Gransha and linkage to existing Cityside Network, 1km This is a looped route, running through the Gransha estate which will also involve provision of a linkage across the Foyle Bridge, and onto the existing Greenway Network at Boom Hall. The section that traverses the Foyle Bridge will be signage only due to the bridge parapet height, with a new link being constructed at the existing east bound layby. The ICT will be expected to submit full planning for this stretch of Greenway. Works would involve but not be limited to upgrading the existing paths to a minimum of 3.0m wide asphalt greenway with appropriate buffer as agreed with DCSDC, kerbing, lighting, drainage, signage, landscaping and ancillary works. The ICT commission for this project will consist of a single contract, to undertake the design development, contract administration and project implementation of the works outlined in Section 1 and undertake the design development, contract administration and project implementation of the works outlined in Section 2. All sections of the works to be developed concurrently. The appointed ICT will be expected to procure and manage separate construction contracts for each section of the works. t Please refer to CfT documents for more detail
CPV: Civil engineering consultancy services · Construction consultancy services · Construction project management services · Construction supervision services · Construction-related services · Highways consultancy services · Structural engineering consultancy services
The lotProcurement structure
single lot · no lot value publishedWhat it takes to wini
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Evaluation split and conditions of participation as published; the tender pack may add morei
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Published sub-criteria (4)
- Methodology: 12%
- Programme: 9%
- Resources: 9%
- price: 70%
Published award criteria (4)
- Methodology: 12
- Programme: 9
- Resources: 9
- Price: 70
- Price carries 70 of 100 points: a 10% discount moves about 7 points. This one is won on the number: sharpen the price before polishing the prose.
Price arithmetic assumes straight proportional scoring; the tender pack may use another formula.
Procedure terms & legal framework
From the official record- Procedure method
- Restricted procedure
- Legal basis
- CELEX · 32014L0024 Public Contracts Regulations 2015 (Directive 2014/24/EU)
- Procurement category
- Services
- Notice status
- Awarded
- Procurement threshold
- Unspecified in notice
- Regulatory regime
- Standard
- Commercial structure
- Stand-alone contract (no framework)
- Competition type
- Competitive procedure
- GPA / WTO covered
- Unspecified in notice
- Recurring procurement
- Unspecified in notice
- First published
- 27 Jul 2021, 12:35 BST
- Last source update
- 27 Jul 2021, 12:35 BST
- FTS notice number
2021/S 000-017785- Classification (CPV)
- Delivery area
- Official registry OCID
ocds-h6vhtk-02cce7Find a Tender
Commercial outcome & contract awards
Published awards, contracts and bid statistics, not a forecast| Awarded to | Value | Date | Status |
|---|---|---|---|
| AECOM LIMITEDContract | £214,210 † | — | Awarded |
Contracts
Contract · AECOM LIMITED
- Signed
- 26 Jul 2021
- Value
- £214,210
- Status
- active
Bid statistics published by the authority
| Bids | SME | VCSE | Valid bid range |
|---|---|---|---|
| 5bids · 5 electronic · 1 from abroad | 0 | — | — |
Contracting authority & participating public bodies
Dispute resolution & review bodies
- The High Courts of Justice of Northern IrelandReview body
Bidders & participating suppliers
1 commercial party on the notice- AECOM LTDAwarded supplier
Official documents & specifications
Official links; attachments are not copiedNo document links were published on the notice.