What is being bought
Published requirement descriptionThe SBDC requires the update of mass spectrometry, chromatography, sample preparation automation and associated equipment and software in a manner compatible with the existing infrastructure.
CPV: Mass spectrometer
The lotProcurement structure
single lot · no lot value publishedLot #1The Stoller Biomarker Discovery Centre (SBDC) was opened in 2016 as a result of…Awarded
The Stoller Biomarker Discovery Centre (SBDC) was opened in 2016 as a result of funding by a philanthropic gift from the Stoller Charitable Trust, the Medical Research Council (MRC) and in partnership with SCIEX, to help to industrialise the process of identifying biomarkers. The Centre was stocked with a large suite of high-end SCIEX mass spectrometers, including TripleTOF® 6600 Systems and QTRAP® 6500+ Systems and associated equipment for clinical proteomics and metabolomics applications. The Centre works to a quality system and has a dedicated IT infrastructure for the management and assessment of the data produced. We are now looking to update the mass spectrometry, chromatography and sample preparation equipment to allow for the relocation of the Centre to a new location with a smaller footprint whilst maintaining the function and infrastructure as much as possible.
Procedure terms & legal framework
From the official record- Procedure method
- Award procedure without prior publication of a call for competition
- Legal basis
- CELEX · 32014L0024 Public Contracts Regulations 2015 (Directive 2014/24/EU)
- Procurement category
- Goods
- Notice status
- Awarded without competition
- Procurement threshold
- Unspecified in notice
- Regulatory regime
- Standard
- Commercial structure
- Stand-alone contract (no framework)
- Competition type
- Direct award (no call for competition)
- GPA / WTO covered
- Yes (GPA)
- Recurring procurement
- Unspecified in notice
- First published
- 7 Apr 2022, 12:14 BST
- Last source update
- 6 May 2022, 08:52 BST
- Authority reference
2022/1878/SBDC/DK/MW- FTS notice number
2022/S 000-011778- Classification (CPV)
- Delivery area
- Official registry OCID
ocds-h6vhtk-032b2fFind a Tender
- Why no open competition
The products involved are manufactured purely for the purpose of research, experiment, study or development under the conditions stated in the directive; The works, supplies or services can be provided only by a particular economic operator due to absence of competition for technical reasons
- Published justification
Explanation: The SBDC was created in partnership with SCIEX and substantial work has been done to configure custom workflows and software tools with the equipment in SBDC. We have very short timeframes for this work and all equipment must be on-site and functioning by the end of July 2022. Hardware and software must therefore be compatible with existing SCIEX technologies.
- Review procedure
The authority will incorporate a minimum 10 calendar days standstill period at the point information on the award of the contract is communicated to tenderers. Applicants who are
unsuccessful shall be informed by the authority as soon as possible after the decision has been made as to the reasons why the applicant was unsuccessful. If an appeal regarding the
award of the contract has not been successfully resolved, the Public Contracts Regulations 2015 (SI 2015 No 102) provide for aggrieved parties who have been harmed or are at risk of
harm by breach of the rules to take action in the High Court (England, Wales and Northern Ireland). Any such action must generally be brought within 3 months. If a declaration of
ineffectiveness is sought, any such action must be brought within 30 days where the authority has communicated the award of the contract and summary of reasons to tenderers or otherwise within 6 months of the contract being entered into. Where a contract has not been entered into, the Court may order the setting aside of the award decision or order the authority to amend any document and may award damages. If the contract has been entered into the Court may, depending on the circumstances, award damages, make a declaration of ineffectiveness, order the authority to pay a fine and/or order the duration of the contract to
be shortened. The purpose of the standstill period referred to is to allow the parties to apply to the Courts to set aside the award decision before the contract is entered into.
Commercial outcome & contract awards
Published awards, contracts and bid statistics, not a forecast| Awarded to | Value | Date | Status |
|---|---|---|---|
| AB Sciex UK Limited | £875,150 †same award published again · counted once | — | Awarded |
| AB Sciex UK Limited | £875,000 † | — | Awarded |
Contracts
Update of equipment within the Stoller Biomarker Discovery Centre (SBDC). · AB Sciex UK Limited
- Signed
- 27 Apr 2022
- Value
- £875,000
- Status
- active
Update of equipment within the Stoller Biomarker Discovery Centre (SBDC). · AB Sciex UK Limited
- Signed
- 7 Apr 2022
- Value
- £875,150
- Status
- active
Bid statistics published by the authority
| Bids | SME | VCSE | Valid bid range |
|---|---|---|---|
| 1bids | — | — | — |
Contracting authority & participating public bodies
Dispute resolution & review bodies
- The High Court of Justice of EnglandReview body
- The University of ManchesterReview contact point
Bidders & participating suppliers
2 commercial parties on the notice- AB Sciex LtdAwarded supplier
- AB Sciex UK LimitedAwarded supplier
Official documents & specifications