Official UK procurement notice
0661 Boars Head Footbridge Superstructure Renewal Works Contract 2026
Authority: Wigan Council (Local council)
What is being bought
Published requirement descriptionBoars Head Footbridge is a three span simply supported steel structure, which carries the footbridge running parallel to the A5106 Chorley Road, over the West Coast Mainline railway line, in Wigan. The deck consists of an existing steel deck, supported by steel trestles located adjacent the up and down lines and bankseat abutments located in the embankments. All are located within the Network Rail Boundary. Wigan Council are seeking tier 1 Network Rail contractors to undertake the following works. The works are to remove the existing steel footbridge structure, refurbish the foundations and banking seats and install a new steel footbridge and supporting trestles. The work includes installing an ACO type drain to the West end of the bridge and minor regrading of the approaches at the East and West Entrances of the bridge. The reconstruction works briefly comprise:
- Installing Traffic Management
- Obtaining all necessary permits and possessions
- Removing surfacing, street lighting and service box
- Protecting services
- Removing the existing steel footbridge and supports
- Checking and making good the concrete surfaces to the trestles and bearing surfaces
- Extending the existing seat structure
- Install new bearing plates and removable deck plates
- Install the new trestles and footbridge
- Install new ACO drain run to West end, connecting into the existing surface water drain
- Replace any kerbs disturbed during the works
- Make good existing footpath surface
- Remove traffic management The Contractor to provide all necessary transport, tools, access equipment, appropriate welfare, water disposal and clearance on completion in order to carry out the works effectively. We require full risk and method statements (RAMS) before commencement. The sites will be under control of CDM 2015.
CPV: Construction work for bridges · Construction work for steel bridges · Footbridge construction work · Railway bridge construction work
The lotProcurement structure
single lot · value publishedLot #1Published value£975,000
- Condition of participation
The bidder, and their Associated Persons identified for this contract, must provide responses to a series of Mandatory and Discretionary Exclusion questions as part of their core supplier information on Find a Tender (Central Digital Platform), and the bidder must respond to Corporate and Professional Standing questions in Section 3 of the Common Assessment Standard. Responses will be assessed in line with the supplier suitability assessment detailed in the Invitation to Tender documentation.
Evidence of financial stability of the bidder assessed in line with the supplier suitability assessment in the Invitation to Tender documentation.
The bidder must hold, or commit to obtain prior to the award of the contract, the following levels of insurance cover: * Employer's Liability Insurance = a minimum of £10million in respect of each and every claim, unlimited in any one year; * Public Liability Insurance = a minimum of £10 million in respect of each and every claim, unlimited in any one year; * Professional Indemnity Insurance = £2 million relating to claims or series of claims arising out of one event; * Contract Works Insurance = to be the full value of this works contract.
Bidders which are classed as a relevant commercial organisation as defined by section 54 ("Transparency in supply chains etc") of the Modern Slavery Act 2015 ("the Act") need to be compliant with the annual reporting requirements contained within Section 54 of the Act 2015.
Tenderers must be accredited as a Network Rail Tier 1 contractor and be able to demonstrate current capability, experience and resources to safely deliver works within the operational railway environment. Tenderers will be required to provide evidence of relevant railway industry accreditations, including RISQS registration where applicable.
The Contractor shall demonstrate a proven track record of successfully delivering comparable rail infrastructure projects, including effective management of railway interfaces, possession planning, safety assurance, and compliance with all applicable Network Rail standards, procedures and requirements. The Employer reserves the right to request supporting evidence of previous project experience and competence of key personnel proposed for the works.
Experience of sub-contractor management - where the bidder is to sub-contract a proportion of the contract, evidence is required to demonstrate maintenance of a healthy supply chain with subcontractors and the procedures used to ensure performance of the contract.
Modern Slavery declaration / Artificial Intelligence declaration, assessed in line with the supplier suitability assessment detailed in the Invitation to Tender documentation.
The bidder will be required to complete/evidence/certify against the 'Common Assessment Standard' question set in line with the assessment methodology detailed in the Invitation to Tender documentation.
What it takes to wini
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Evaluation split and conditions of participation as published; the tender pack may add morei
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Published sub-criteria (2)
- Quality and Social Value: 40%
- Price: 60%
Published award criteria (2)
- Quality and Social Value: The Quality Award Criteria will assess Experience, Resource Availability, Management of the Works and Social Value.
- Price: Overall cost of the tenderers submission
- Condition of participation
The bidder, and their Associated Persons identified for this contract, must provide responses to a series of Mandatory and Discretionary Exclusion questions as part of their core supplier information on Find a Tender (Central Digital Platform), and the bidder must respond to Corporate and Professional Standing questions in Section 3 of the Common Assessment Standard. Responses will be assessed in line with the supplier suitability assessment detailed in the Invitation to Tender documentation.
Evidence of financial stability of the bidder assessed in line with the supplier suitability assessment in the Invitation to Tender documentation.
The bidder must hold, or commit to obtain prior to the award of the contract, the following levels of insurance cover: * Employer's Liability Insurance = a minimum of £10million in respect of each and every claim, unlimited in any one year; * Public Liability Insurance = a minimum of £10 million in respect of each and every claim, unlimited in any one year; * Professional Indemnity Insurance = £2 million relating to claims or series of claims arising out of one event; * Contract Works Insurance = to be the full value of this works contract.
Bidders which are classed as a relevant commercial organisation as defined by section 54 ("Transparency in supply chains etc") of the Modern Slavery Act 2015 ("the Act") need to be compliant with the annual reporting requirements contained within Section 54 of the Act 2015.
Tenderers must be accredited as …
- Price carries 60 of 100 points: a 10% discount moves about 6 points. This one is won on the number: sharpen the price before polishing the prose.
- Turnover usually expected at this size: about £1,950,000 (twice the annual value).
Price arithmetic assumes straight proportional scoring; the tender pack may use another formula. Turnover is an indicative market norm (≈2× annual value), not a published condition.
Competition analysis · published record, not a forecast of who will bid
How Wigan Council buys Engineering works and construction works (CPV 4522), and who usually turns up
Wigan Council’s published record next to the market for the same work. Frameworks and DPS are left out: they draw different bid counts. Whole-market view: Engineering works and construction works (CPV 4522) →
How the contest usually goes
Winner shares use published awards; bid and price charts use contested lots.
i
How often small and medium firms win.
Share of awards where the winner’s size is known.
The counts under this question show how many awards have a known supplier size.
Small firms have won here. Neither number says whether you qualify; it describes who has been winning.
i
How often local firms win similar work.
Winners with a registered address in the delivery region, out of awards with a known address.
Local means the winner is registered in the region where that award was delivered.
A local branch does not count if the registered address is elsewhere.
Most of this buyer’s recorded winners were registered outside the region where that award was delivered.
i
How long buyers here take to decide after bids close.
Middle value in days from the bid deadline to the award date, on competitions that published both.
Only decided tenders count, so slow ones still waiting are not in.
Half of these awards have an award date within 39 days of the bid deadline.
i
How often work is awarded with no recorded rival.
Direct awards and tenders where every published lot count shows one bid.
The market share is a minimum: some awards have no bid count.
Thin markets produce this too; it is not proof of a tailored specification.
Awards are recorded, but published direct routes and bid counts do not establish this buyer’s share.
How many bids did past lots attract?
i
How many bids past lots received.
Each colour is a bid-count range. Only competed lots with a published count are included.
Past bids do not predict this tender.
1 bid0% / 19%
2–344% / 48%
4–633% / 29%
7+22% / 3%
How did awards compare with estimates?
i
Where winning prices landed against estimates.
Each colour shows awards below, close to or above the published estimate, one lot at a time.
Past prices are a guide, not a bid price.
Below estimate0% / 62%
Within ±2%83% / 19%
Above estimate17% / 19%
Assess each lot i
What past awards tell you about each lot.
See the forecast, this buyer’s earlier suppliers and firms with relevant wins.
No supplier is confirmed as a bidder.
i
What past awards tell you about each lot.
See the forecast, this buyer’s earlier suppliers and firms with relevant wins.
No supplier is confirmed as a bidder.
Open a lot for its forecast, this buyer’s previous supplier and possible competitors, from published award history, not a bid list
Lot #1CPV 4522Published estimate£975k
i
How many bids this lot may attract.
The forecast uses similar past competitions. The bar shows either that forecast or past bid counts; the line below says which.
Each lot shows its own forecast based on its own category; forecasts for different lots of the same notice are not comparative.
A forecast, not a list of bidders.
1 bid5%
2–349%
4–640%
7+5%
i
Where the award price may land.
The forecast uses similar awards and the buyer’s estimate. The band covers the middle half of likely prices.
Based on 183 comparable awards. Each lot reflects its own category; forecasts for different lots of the same notice are not comparative.
A statistical guide from past awards, not a price to bid.
Middle 50%£829k–£975k
Estimate£975k
Who has supplied this buyer on similar work? i
Who has done similar work for this buyer.
Past contracts are matched by buyer, title and type of work.
A past supplier may not bid again.
i
Who has done similar work for this buyer.
Past contracts are matched by buyer, title and type of work.
A past supplier may not bid again.
| Supplier | This buyer’s earlier contract | Lot | Award value | Why listed |
|---|---|---|---|---|
| H.H. SMITH & SONS CO LTDWorked for this buyer | Haigh Woodland Park - Bothy Cottages and Events Venue Restoration and New Build Constructionruns to Dec 2026 | — | £5.6m | Similar wording and category |
| Hughes Brothers (Building & Joinery) LtdWorked for this buyer | Wigan Council - Simple Major Adaptations Framework 2025 - 2029notice published Jun 2025 | External works | — | Similar wording and category |
| UPS Building and Maintenance limitedWorked for this buyer | Wigan Council - Simple Major Adaptations Framework 2025 - 2029notice published Jun 2025 | External works | — | Similar wording and category |
| AGR Building and Fencing Contractors LtdWorked for this buyer | Wigan Council - Simple Major Adaptations Framework 2025 - 2029notice published Jun 2025 | External works | — | Similar wording and category |
Who could compete for this lot? i
Who could compete for this lot?
Firms with relevant past wins. On a framework, we show firms on that agreement.
None is confirmed as a bidder.
i
Who could compete for this lot?
Firms with relevant past wins. On a framework, we show firms on that agreement.
None is confirmed as a bidder.
| Supplier | Won in this category | Live contracts | Award vs estimate |
|---|---|---|---|
| 1 award in 36m · last 19 months ago | None on file | no comparable pairs | |
| £228m39 awards in 36m · last 1 month ago | 17 live · £1.1bn iPublic contracts this supplier still holds. Its awards whose published end date is still in the future, with their values. Many contracts publish no end date, so this is a floor, not the whole book. Unexpired says nothing about spare capacity. | at estimate n=5 | |
| £135m27 awards in 36m · last this month | 16 live · £9.0m iPublic contracts this supplier still holds. Its awards whose published end date is still in the future, with their values. Many contracts publish no end date, so this is a floor, not the whole book. Unexpired says nothing about spare capacity. | no comparable pairs | |
| £848k11 awards in 36m · last 3 months ago | 1 live · £914k iPublic contracts this supplier still holds. Its awards whose published end date is still in the future, with their values. Many contracts publish no end date, so this is a floor, not the whole book. Unexpired says nothing about spare capacity. | 10% above n=2 | |
| £15m4 awards in 36m · last 10 months ago | 1 live iPublic contracts this supplier still holds. Its awards whose published end date is still in the future, with their values. Many contracts publish no end date, so this is a floor, not the whole book. Unexpired says nothing about spare capacity. | no comparable pairs |
About this data
- Source. Official UK public procurement notices (Find a Tender), reused under the Open Government Licence v3.0. New notices arrive through the day; the figures are rebuilt nightly.
- Two views, kept apart. The authority’s own track record and the wider market for the same kind of work sit side by side and are never mixed. Where the local picture is too thin, a figure widens to a broader market and says which one it used.
- Forecasts are labelled. The price forecast and its range, possible competitors and the earlier-work matches are our estimates from past awards: not published facts, not win chances and not price advice. Official notices do not say who is bidding.
- Every figure shows what it rests on. Not every notice publishes a bid count, a value or a delivery region, so each figure carries the number of records behind it, and one built on few records is marked as such. The on a figure explains it; the counting rules are in the methodology. Spotted something wrong? Tell us.
Procedure terms & legal framework
From the official record- Procedure method
- Below threshold - open competition
- Legal basis
- UKPGA · 2023/54 Procurement Act 2023
- Procurement category
- Works
- Notice status
- Open for tender
- Procurement threshold
- Below threshold
- Regulatory regime
- Standard
- Commercial structure
- Stand-alone contract (no framework)
- Competition type
- Competitive procedure
- GPA / WTO covered
- Unspecified in notice
- Recurring procurement
- Unspecified in notice
- First published
- 7 Oct 2026, 13:51 BST
- Last source update
- 8 Oct 2026, 13:00 BST
- Authority reference
DN827563- FTS notice number
2026/S 000-094763- Latest notice
- Tender notice (UK4)
- Classification (CPV)
- Delivery area
- Official registry OCID
ocds-h6vhtk-0782bdFind a Tender
How to participate & submission route
Official notice Submit via ProContract (Due North)- Requests to participate (first stage)
- —
- Tender submission deadline
- 20 Nov 2026, 12:00 GMT
- Clarification deadline
- 13 Nov 2026, 12:00 GMT
- Submission channel
- Official e-sourcing portal
- Electronic submission
- Allowed
For tenders to be submitted electronically please visit website www.the-chest.org.uk ↗
Timeline
7 Oct 2026 → 5 Apr 2027 · 4 dates- Tender notice published21 days ago7 Oct 2026, 13:51 BST
- Today28 Oct 2026
- Clarification questions byin 15 days13 Nov 2026, 12:00 GMT
- Submission deadlinein 22 days20 Nov 2026, 12:00 GMT
- Contract startsin 158 days5 Apr 2027, 00:00 BST
Notice history
2 events · 2 releases on Find a Tender · since 7 Oct 2026- Tender notice published7 Oct 2026, 13:51 BSTUK4
- Tender notice published8 Oct 2026, 13:00 BSTUK4
Published amendments (1)
Additional details relating to Conditions of Participation in 'Participation' section added and revised wording to explain the Quality assessment within the 'Award Criteria' section.
Commercial outcome & contract awards
Nothing awarded yet- Awards (0)
- No award published
- Contracts (0)
- No contract published
- Bid statistics
- No aggregate bid statistics published
Contracting authority & participating public bodies
Official documents & specifications (2)
Official links; attachments are not copiedNotices published for this procedure
- Tender notice Tender notice on Find a Tender
- Tender notice Tender notice on Find a Tender