Find a TenderAwarded without competition
Published 12 Aug 2025, 10:04 BST

Official UK procurement notice

Asset Delivery (AD12) Maintenance & Response Contract Cr

Official notice

Authority: National Highways Limited (Central government)

WorksAward procedure without prior publication of a call for competition
Awarded value£257,250,000published contract · exc. VAT
Awarded 30 Nov 2020no call for competition
Awarded to Amey OW Limited

What is being bought

Published requirement description

This VEAT Notice relates to a Deed of Variation to a National Highways' Maintenance and Response Contract. This Contract currently provides and undertakes all cyclical and reactive maintenance, incident response, defect rectification and severe weather delivery on the trunk roads and motorways within Yorkshire & Humber (National Highways Area 12) (the "Contract"). Duties also include maintenance of roadside technology, the provision of traffic management for the contractor, maintenance and incident response activities, and traffic management for others who may be working on the network

The variation will add a section of the M1-A1, Lofthouse to Bramham into the Contract which is currently maintained under a Design Build Finance & Operate ("DBFO") contract which is due to expire on 25 March 2026. Consequently the total value of the Contract will increase by approximately 44%. It will also shorten the Contract which will have a new end date of 1st August 2028 instead of 6 June 2029 in order to align with the procurement process for the next Maintenance & Response contracts.

CPV: Construction work for highways · Electrical installation work · Engineering services · Highway maintenance work · Installation of signalling equipment · Miscellaneous repair and maintenance services · Repair, maintenance and associated services related to roads and other equipment · Road traffic-control equipment · Road-maintenance works · Roadworks · Surface work for highways

The lotProcurement structure

single lot · no lot value published
Lot #1A Design Build Finance Operate (DBFO) contract covers M1-A1 and expires on 25th March 2026

A Design Build Finance Operate (DBFO) contract covers M1-A1 and expires on 25th March 2026. National Highways therefore must appoint an alternative maintenance contractor and it considers that the scope of these works is already included within this existing Maintenance and Response Contract which is adjacent geographically. Therefore these roads will be incorporated into this existing Maintenance and Response (M&R) Contract for Area 12 of the Strategic Road Network following the award of the Deed of Variation. This together with the need for national alignment of the expiry dates for all of the M&R contracts, ready for their re-procurement, means that the term of the Area 12 M&R Contract will be shortened and will have a new end date of 1st August 2028 instead of 06th June 2029. The new estimated total Contract value will be £ 257,250,000.

Delivery: UK, Yorkshire & Humber · Yorkshire and the Humber Region (Highways England Area 12)

Procedure terms & legal framework

From the official record
Procedure method
Award procedure without prior publication of a call for competition
Legal basis
CELEX · 32014L0024 Public Contracts Regulations 2015 (Directive 2014/24/EU)
Procurement category
Works
Notice status
Awarded without competition
Procurement threshold
Unspecified in notice
Regulatory regime
Standard
Commercial structure
Stand-alone contract (no framework)
Competition type
Direct award (no call for competition)
GPA / WTO covered
Yes (GPA)
Recurring procurement
Unspecified in notice
First published
12 Aug 2025, 10:04 BST
Last source update
12 Aug 2025, 10:04 BST
FTS notice number
2025/S 000-047879
Classification (CPV)
Construction work for highwaysElectrical installation workEngineering servicesHighway maintenance workInstallation of signalling equipmentMiscellaneous repair and maintenance servicesRepair, maintenance and associated services related to roads and other equipmentRoad traffic-control equipmentRoad-maintenance worksRoadworks
+1 moreSurface work for highways
Delivery area
UKYorkshire & Humber (UKE)
Official registry OCID
ocds-h6vhtk-0585b3 Find a Tender
Why no open competition
The procurement falls outside the scope of application of the directive
Published justification

The modifications to the Contract fall within the permissible grounds set out under Regulation 72(1)(e) of the Public Contracts Regulations 2015 in that the modifications are not substantial within the meaning of Regulation 72(8) of the Public Contracts Regulations 2015 because:

The inclusion of Design Build Finance and Operate (DBFO) roads into the Contract does not render the Contract materially different compared to when it was originally procured. The type of work originally required of the Contract (i.e. maintenance and response) is the same as that which it will carry out on the previous DBFO stretches of the Strategic Road Network, it is just a case that the total lane coverage to be maintained under the Contract increases.

Adding the additional roads would not have changed the outcome of the original procurement in any way. The Contract will be fully operated in accordance with their current terms and pricing;

As the current Contract will be operated for the new roads on the same terms and pricing, this does not alter the economic balance of the Contract in favour of the contractor;

The change does not considerably alter the scope of the Contract as the works and services provided will remain unchanged and the roads have been included in this Contract because they are adjacent in terms of geographical scope also. Any increase in scope is also mitigated by a shortening in Contract term;

This is not a change in contractor.

In addition, National Highways also considers that the exemption at Regulation 72(1)(b) would in any event apply. This permits additional services or supplies that have become necessary and were not included in the initial procurement where a change of contractor cannot be made for economic or technical reasons and another supplier/procurement would cause significant inconvenience or substantial duplication of costs for the contracting authority; and where any increase in price does not exceed 50% of the value of the original Contract.

The Deed of Variation ensures continuity of service on the Strategic Road Network and aligns with National Highways' wider asset delivery and procurement strategy, thereby safeguarding public value and network integrity. The Contract is being shortened to better align with the re-procurement strategy for all Maintenance & Response contracts. It would provide significant technical difficulties and duplication of procurement costs for National Highways to procure a contractor simply for this short stretch of network given the current re-procurement strategy.

Commercial outcome & contract awards

Published awards, contracts and bid statistics, not a forecast
Awards 1
Awarded value £257,250,0001 contract exc. VAT
Contracts signed 1latest 30 Nov 2020
Awarded toValueDateStatus
Amey OW LimitedSubcontracting: declared£257,250,000 †—Awarded

Contracts

  • Contract 047879-2025-1 · Amey OW Limited

    Signed
    30 Nov 2020
    Value
    £257,250,000
    Status
    active

Contracting authority & participating public bodies

National Highways

Contracting authorityCentral GovernmentNational or federal agency/officeGeneral public services Bridge House, Walnut Tree Close, Guildford, UK, GU1 4LZContact email, phone

Bidders & participating suppliers

1 commercial party on the notice

Official documents & specifications

Official links; attachments are not copied

No document links were published on the notice.