What is being bought
Published requirement descriptionMilton Keynes College (The Employer) wishes to procure the design and construction of the
following works:
Tariff Funded Scope
A. Refurbishment and expansion of existing facilities comprising the following works:
B. Construction and fit-out of new ground and first floor accommodation within the existing Motor Vehicle Workshop building including new stairs, platform lift, WC accommodation and
associated mechanical and electrical services.
C. Reconfiguration and refurbishment of the existing Main Building Motor Vehicle Workshop including new external glazing to replace existing vehicle access door, creation of two new classrooms and an ICT room and associated mechanical and electrical services.
Carbon Offset Funded Scope
New Air Source Heat Pump installation comprising the following works:
A. Construction of a new external plant compound.
B. Construction of a new enclosed plantroom adjoining the south end of the existing Motor Vehicle Workshop building.
C. Installation of new Air Source Heat Pump plant
D. Installation of associated buffer vessels, pumps, ancillary plant, pipework, valves and accessories
E. Provision of electrical services including power, fire alarm and controls.
F. Modifications to the existing gas boiler installation.
CPV: Construction work for buildings of further education
The lotProcurement structure
single lot · value publishedLot #1AwardedPublished value£2,000,000
- Condition of participation
The full tender pack can be requested from Craig Pullen, Procurement Consultant by email at craig@cpconsulting.org.uk
What it takes to wini
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Evaluation split and conditions of participation as published; the tender pack may add morei
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Lot awarding rule: Award will be made on the following criteria: Quality 60% Price 40% Full evaluation criteria is included in the ITT
- Condition of participation
The full tender pack can be requested from Craig Pullen, Procurement Consultant by email at craig@cpconsulting.org.uk
Procedure terms & legal framework
From the official record- Procedure method
- Below threshold - open competition
- Legal basis
- UKPGA · 2023/54 Procurement Act 2023
- Procurement category
- Works
- Notice status
- Awarded
- Procurement threshold
- Below threshold
- Regulatory regime
- Standard
- Commercial structure
- Stand-alone contract (no framework)
- Competition type
- Competitive procedure
- GPA / WTO covered
- Unspecified in notice
- Recurring procurement
- Unspecified in notice
- First published
- 7 Apr 2025, 16:43 BST
- Last source update
- 29 May 2025, 16:15 BST
- FTS notice number
2025/S 000-013484- Latest notice
- Contract award notice (UK6)
- Classification (CPV)
- Delivery area
- Official registry OCID
ocds-h6vhtk-04fe55Find a Tender
How it was run
Official notice- Submission deadline
- 9 May 2025, 12:00 BST
- Clarification deadline
- 1 May 2025, 12:00 BST
- Electronic submission
- Not allowed
Tenders must be submitted to projectprocurement@mkcollege.ac.uk - no other form of submission will be accepted. Full details are included in the ITT.
Timeline
7 Apr 2025 → 2 Jun 2025 · 5 dates- Tender notice published7 Apr 2025, 16:43 BST
- Clarification questions by1 May 2025, 12:00 BST
- Submission deadline9 May 2025, 12:00 BST
- Latest notice published29 May 2025, 16:15 BST
- Contract starts2 Jun 2025, 00:00 BST
Notice history
4 events · 2 releases on Find a Tender · since 7 Apr 2025- Tender notice published7 Apr 2025, 16:43 BSTUK4
- Contract award notice published29 May 2025, 16:15 BSTUK6
- Status changed to complete29 May 2025, 16:15 BST
- Contract signature expected2 Jun 2025, 23:59 BSTscheduled
Commercial outcome & contract awards
Published awards, contracts and bid statistics, not a forecast| Awarded to | Value | Date | Status |
|---|---|---|---|
| Borras Construction LtdSME7 Jul 2025 – 29 Aug 2025 | £1,733,710 | 29 May 2025 | Awarded |
Bid statistics published by the authority
| Bids | SME | VCSE | Valid bid range |
|---|---|---|---|
| 11final-stage tenders | 11 | 0 | — |
Contracting authority & participating public bodies
Bidders & participating suppliers
1 commercial party on the notice- BORRAS CONSTRUCTION LTD.Awarded supplier
Official documents & specifications (2)
Official links; attachments are not copiedNotices published for this procedure
- Contract award notice Contract award notice on Find a Tender
- Tender notice Tender notice on Find a Tender