Find a TenderRequests to participate open Tender notice
Published 9 Oct 2026, 18:33 BST

Official UK procurement notice

ITT - Swindon Archive Decarbonisation Design Team (UID 320)

Authority: Historic England (Central government)

Two-stageServicesCompetitive flexible procedureAbove threshold
Sectors: Construction & Civil Engineering (45)Architecture & Engineering (71) Delivery: Delivery location not published
Published estimate£149,000£178,000 inc. VAT
Submission deadline 4 Nov 202609:30 GMT · 7 days left
Clarification cut-off 28 Oct 202617:00 GMT · questions to the authority
Contract term 8 moends 30 Sept 2027 · up to 30 Aug 2028 with extensions · starts 28 Jan 2027

What is being bought

Published requirement description

Historic England is seeking to appoint a multidisciplinary design team to develop the Archive Decarbonisation Project at its national archive facility in Swindon through RIBA Stage 3. Under the terms of this contract, we reserve the right to award RIBA stage 4 following the satisfactory completion of stage 3 and the receipt of an acceptable return for Stage 4 methodology and pricing schedule (in line with rates provided at stage 3).

The Historic England Archive is one of the nation's most significant collections of records relating to England's historic environment. The purpose-built archive store was constructed in 1993 to BS5454 standards and provides specialist environmental conditions for the long-term preservation of nationally important photographic, film and documentary collections. However, the building and its associated mechanical and electrical systems were not designed with energy efficiency or net-zero objectives in mind.

The project forms a key part of Historic England's commitment to achieve net-zero carbon emissions by 2040 and responds to the urgent requirement to replace ageing building services plant that has reached, and in some cases exceeded, its operational life. Recent equipment failures have highlighted the increasing risk to collection preservation, building resilience and operational continuity.

A RIBA Stage 2 feasibility study has recently been completed. The study explored a range of options to reduce operational carbon, improve energy performance and secure the long-term sustainability of the archive while maintaining stringent environmental conditions required for collection care.

Based on the information provided, Historic England's preferred option currently involves:

  • Replacement of existing end-of-life environmental control systems with significantly more energy-efficient solutions.
  • Rationalisation of archive environmental zones to improve operational efficiency.
  • Fabric improvements to enhance thermal performance and airtightness.
  • Fire safety upgrades and associated building works.
  • Creation of additional archive storage capacity through the repurposing of existing plant room space, reducing reliance on external storage facilities and supporting future collection growth.

Scope of Services

The appointed design team will be required to lead the project through:

RIBA Stage 3 – Spatial Coordination

Including but not limited to:

  • Review and validation of the completed RIBA Stage 2 outputs.
  • Development of the preferred design solution.
  • Coordination of architectural, structural and building services design, ensuring full integration of archive operational, conservation and storage requirements, and compliance with relevant standards and guidance, including BS EN 16893:2018 Evaluation and mitigation of collection care risks associated with proposed mechanical solutions.
  • Interpretation and integration of thermographic surveys, air-tightness testing and other specialist investigations.
  • Use and develop the client-provided Revit BIM model as the principal tool for multidisciplinary spatial coordination, ensuring that all proposed building-services systems, plant, access requirements and interfaces are accurately modelled and coordinated with the architectural and structural design.
  • Review, validate and develop the existing building physics model to a level appropriate for RIBA Stage 3, reflecting the spatially coordinated design and demonstrating performance against the agreed environmental requirements, energy and carbon targets, plant loads and future climate scenarios.
  • Planning application preparation and submission.
  • Cost planning and value management exercises.
  • Development of a robust whole-life cost and carbon assessment.
  • Stakeholder engagement and workshop facilitation.
  • Support Historic England’s fundraising activities for the project by providing reasonable information, evidence, and documentation to assist fundraising and grant applications where requested.
  • How the procedure runs: Stage 1 - Using Procurement Specific Questionnaire (Conditions of participation) to reduce the number of suppliers to be invited to submit final tenders. If supplier passes all Stage 1 questions, then they will be invited to participate to Stage 2. Stage 2 - Invitation To Tender (ITT) - Quality and Pricing evaluation questions.

CPV: Architectural and related services · Architectural design services · Architectural, engineering and planning services · Engineering design services · Environmental engineering consultancy services · Environmental improvement works · Project and design preparation, estimation of costs

The lotProcurement structure

single lot · value published
Lot #1Renewal 8 moPublished value£149,000
Contract period: 28 Jan 2027 – 30 Sept 2027 (8 mo) · up to 30 Aug 2028 with extensionsValue: £149,000 exc. VAT · £178,000 inc. VAT
Turnover guideline: ~£298,000/yr≈ 2× annual value
Extensions: RIBA stage 4 - we reserve the right to award RIBA stage 4 following the satisfactory completion of stage 3 and the receipt of an acceptable return for Stage 4 methodology and pricing schedule (in line with rates provided at stage 3).

Who is likely to bid for this lot ↓

What it takes to win
i

How this buyer will score bids.

The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).

Evaluation split and conditions of participation as published; the tender pack may add more
How bids are scored
Quality: 70%Price: 30%
Published sub-criteria (2)
  • Quality: 70%
  • Pricing: 30%
Published award criteria (2)
  • Pricing: RIBA Stage 3 fixed price schedule RIBA Stage 3 Rate table RIBA Stage 4 Rate table
  • Quality: Quality 1 - Understanding of Project Objectives and Option Review Approach Quality 2 - Methodology for Option Validation, Design Development and Technical Delivery Quality 3 - Understanding of Archive Collection Requirements Quality 4 - Archive Collections and Environmental Risk Management Quality 5 - Relevant Experience and Lessons Learned Quality 6 - Cost Management and Buildability Quality 7 - Project Team and Resource Commitment Social Value 1 - Environmental stewardship, skills and wider benefit

No conditions of participation were published on the notice; check the tender documents.

What this means for your bid
  • Price carries 30 of 100 points: a 10% discount moves about 3 points. The method statement decides this lot, not the discount.
  • Turnover usually expected at this size: about £298,000 (twice the annual value).

Price arithmetic assumes straight proportional scoring; the tender pack may use another formula. Turnover is an indicative market norm (≈2× annual value), not a published condition.

Competition analysis · published record, not a forecast of who will bid

How Historic England buys Consultative engineering and construction services (CPV 7131), and who usually turns up

Historic England’s published record next to the market for the same work. Frameworks and DPS are left out: they draw different bid counts. Whole-market view: Consultative engineering and construction services (CPV 7131) →

1

How the contest usually goes

Winner shares use published awards; bid and price charts use contested lots.

Question for the bid
This buyerHistoric England · division 71
The marketConsultative engineering and construction services (CPV 7131) · South West England (authority’s region)
What to do with it
How often do SMEs win?
i

How often small and medium firms win.

Share of awards where the winner’s size is known.

The counts under this question show how many awards have a known supplier size.

Last 36 months.

Buyer: 8 of 13 known-size awards · market: CPV 7131 · South West England (authority’s region), n=172
62%66%

Small firms have won here. Neither number says whether you qualify; it describes who has been winning.

How often do local suppliers win?
i

How often local firms win similar work.

Winners with a registered address in the delivery region, out of awards with a known address.

Local means the winner is registered in the region where that award was delivered. The market figure counts awards delivered in South West England (authority’s region).

A local branch does not count if the registered address is elsewhere.

Last 36 months.

Buyer: 7 of 8 known-location awards · market: CPV 7131 · South West England (authority’s region), n=226
88%28%

Most of this buyer’s recorded winners were registered in the region where that award was delivered.

How long to a decision?
i

How long buyers here take to decide after bids close.

Middle value in days from the bid deadline to the award date, on competitions that published both.

Only decided tenders count, so slow ones still waiting are not in.

Last 36 months.

Buyer: no decision dates published · market: CPV 7131 · South West England (authority’s region), n=35
—54 days

Half of these awards have an award date within 54 days of the bid deadline.

How often single-bid or direct?
i

How often work is awarded with no recorded rival.

Direct awards and tenders where every published lot count shows one bid.

Both shares are minimums: some awards have no bid count.

Thin markets produce this too; it is not proof of a tailored specification.

Last 36 months.

Buyer: at least 7 of 16 procurements with awards had no recorded rival · market: CPV 7131 · South West England (authority’s region), n=239
44%51%

Direct awards or one recorded bid are common here. Check the route before spending time on a bid.

How many bids did past lots attract?

i

How many bids past lots received.

Each colour is a bid-count range. Only competed lots with a published count are included.

Past bids do not predict this tender.

Last 36 months.

This buyer13 lots with bid counts · all categories
31% had one bid
The market48 lots with bid counts · CPV 7131 · South West England (authority’s region)
21% had one bid
Buyer / market · select a colour for counts
1 bid31% / 21%
Buyer: 4 of 13 lots with published bid counts. Market: 10 of 48 lots with published bid counts.
2–315% / 6%
Buyer: 2 of 13 lots with published bid counts. Market: 3 of 48 lots with published bid counts.
4–615% / 29%
Buyer: 2 of 13 lots with published bid counts. Market: 14 of 48 lots with published bid counts.
7+38% / 44%
Buyer: 5 of 13 lots with published bid counts. Market: 21 of 48 lots with published bid counts.

How did awards compare with estimates?

i

Where winning prices landed against estimates.

Each colour shows awards below, close to or above the published estimate, one lot at a time.

Past prices are a guide, not a bid price.

Last 36 months.

This buyer43 lots with estimate and award · all categories
37% below estimate
The market39 lots with estimate and award · CPV 7131 · South West England (authority’s region)
38% below estimate
Buyer / market · select a colour for counts
Below estimate37% / 38%
Buyer: 16 of 43 lots with an estimate and award. Market: 15 of 39 lots with an estimate and award.
Within ±2%53% / 44%
Buyer: 23 of 43 lots with an estimate and award. Market: 17 of 39 lots with an estimate and award.
Above estimate9% / 18%
Buyer: 4 of 43 lots with an estimate and award. Market: 7 of 39 lots with an estimate and award.
2

Assess each lot
i

What past awards tell you about each lot.

See the forecast, this buyer’s earlier suppliers and firms with relevant wins.

No supplier is confirmed as a bidder.

Open a lot for its forecast, this buyer’s previous supplier and possible competitors, from published award history, not a bid list

Lot #1CPV 45268 monthsPublished estimate£149k

This lot is listed as CPV 4526. The table above uses the notice category.

Expected competition
i

How many bids this lot may attract.

The forecast uses similar past competitions. The bar shows either that forecast or past bid counts; the line below says which.

Each lot shows its own forecast based on its own category; forecasts for different lots of the same notice are not comparative.

A forecast, not a list of bidders.

6expected bids23% chance of a single bid
similar past contests in this category: 53
Forecast chances for this lot
1 bid23%
Chance this lot gets 1 bid: 23%. This is a forecast.
2–322%
Chance this lot gets 2–3: 22%. This is a forecast.
4–630%
Chance this lot gets 4–6: 30%. This is a forecast.
7+25%
Chance this lot gets 7+: 25%. This is a forecast.
Commercial price forecast
i

Where the award price may land.

The forecast uses similar awards and the buyer’s estimate. The band covers the middle half of likely prices.

Based on 24 comparable awards. Each lot reflects its own category; forecasts for different lots of the same notice are not comparative.

A statistical guide from past awards, not a price to bid.

£139k6% below estimate
24 comparable awards
Forecast compared with the buyer’s estimate
Middle 50%£124k–£149k
Half of likely prices fall between £123,578 and £149,000.
Estimate£149k
The buyer published an estimate of £149,000 for this lot.
A 23% chance the award lands exactly on the estimate.

Who has supplied this buyer on similar work?
i

Who has done similar work for this buyer.

Past contracts are matched by buyer, title and type of work.

A past supplier may not bid again.

SupplierThis buyer’s earlier contractLotAward valueWhy listed
Milton Keynes Surveys LtdLive contractITT - Swindon Archive Decarbonisation - Measured Building Survey (UID 312)runs to Oct 2026—£13kMatched as the earlier contract
ArchitypeWorked for this buyerArchive Decarbonisation Surveys and Reports (NP 368)notice published Oct 2025——Similar wording and category
NDM Health LtdWorked for this buyerRFQ - Technical retrofit training for architects, surveyors, and SPAB helpline (UID 146)notice published Jan 2026——Similar wording and category

Who could compete for this lot?
i

Who could compete for this lot?

Firms with relevant past wins. On a framework, we show firms on that agreement.

None is confirmed as a bidder.

Restricted route (Stage 2 ITT / Shortlist): Bidding is restricted to invited candidates who qualified at Stage 1. Uninvited suppliers cannot participate in this round.
SupplierWon in this categoryLive contractsAward vs estimate
Live contract
£13k1 award in 36m · last 2 months ago1 live · £13k
i

Public contracts this supplier still holds.

Its awards whose published end date is still in the future, with their values. Many contracts publish no end date, so this is a floor, not the whole book.

Unexpired says nothing about spare capacity.

no comparable pairs
£70k1 award in 36m · last 12 months agoNone on file26% below n=1
33 panel places
£60m134 awards in 36m · last this month33 live · £19m
i

Public contracts this supplier still holds.

Its awards whose published end date is still in the future, with their values. Many contracts publish no end date, so this is a floor, not the whole book.

Unexpired says nothing about spare capacity.

at estimate n=27
24 panel places
£20m86 awards in 36m · last this month20 live · £6.5m
i

Public contracts this supplier still holds.

Its awards whose published end date is still in the future, with their values. Many contracts publish no end date, so this is a floor, not the whole book.

Unexpired says nothing about spare capacity.

3% below n=2
4 panel places
£7.8m14 awards in 36m · last this month10 live · £8.5m
i

Public contracts this supplier still holds.

Its awards whose published end date is still in the future, with their values. Many contracts publish no end date, so this is a floor, not the whole book.

Unexpired says nothing about spare capacity.

9% above n=5
About this data
  • Source. Official UK public procurement notices (Find a Tender), reused under the Open Government Licence v3.0. New notices arrive through the day; the figures are rebuilt nightly.
  • Two views, kept apart. The authority’s own track record and the wider market for the same kind of work sit side by side and are never mixed. Where the local picture is too thin, a figure widens to a broader market and says which one it used.
  • Forecasts are labelled. The price forecast and its range, possible competitors and the earlier-work matches are our estimates from past awards: not published facts, not win chances and not price advice. Official notices do not say who is bidding.
  • Every figure shows what it rests on. Not every notice publishes a bid count, a value or a delivery region, so each figure carries the number of records behind it, and one built on few records is marked as such. The on a figure explains it; the counting rules are in the methodology. Spotted something wrong? Tell us.

What this replaces
i

Who has done similar work for this buyer.

Past contracts are matched by buyer, title and type of work.

51% title match.

A past supplier may not bid again.

The prior contract this notice most likely re-tenders · matched by title and category (51% title match), the holder is not guaranteed to re-bid

ITT - Swindon Archive Decarbonisation - Measured Building Survey (UID 312) — held by Milton Keynes Surveys Ltd; the published contract ends 31 Oct 2026.

Procedure terms & legal framework

From the official record
Procedure method
Competitive flexible procedure
Legal basis
UKPGA · 2023/54 Procurement Act 2023
Procurement category
Services
Notice status
Requests to participate open
Procurement threshold
Above threshold (FTS publication)
Regulatory regime
Standard
Commercial structure
Stand-alone contract (no framework)
Competition type
Competitive procedure
GPA / WTO covered
Unspecified in notice
Recurring procurement
Unspecified in notice
First published
9 Oct 2026, 18:33 BST
Last source update
9 Oct 2026, 18:33 BST
Award evaluation window
Submission end – 12 Jan 2027
Authority reference
P/REF 00000632
FTS notice number
2026/S 000-095864
Latest notice
Tender notice (UK4)
Classification (CPV)
Architectural and related servicesArchitectural design servicesArchitectural, engineering and planning servicesEngineering design servicesEnvironmental engineering consultancy servicesEnvironmental improvement worksProject and design preparation, estimation of costs
Delivery area
Not published
Official registry OCID
ocds-h6vhtk-078534 Find a Tender
How it runs

Stage 1 - Using Procurement Specific Questionnaire (Conditions of participation) to reduce the number of suppliers to be invited to submit final tenders. If supplier passes all Stage 1 questions, then they will be invited to participate to Stage 2.

Stage 2 - Invitation To Tender (ITT) - Quality and Pricing evaluation questions.

How to participate & submission route

Official notice Submit via In-tend
Submission portal named on this notice: In-tend · Who buys & how to bid on In-tend
Supplier login requiredElectronic submission allowedLanguage: EN
Access & registration note: Free · one account per buying organisation's portal · reCAPTCHA on signup
Requests to participate (first stage)
4 Nov 2026, 09:30 GMT
Tender submission deadline
4 Nov 2026, 09:30 GMT
Clarification deadline
28 Oct 2026, 17:00 GMT
Submission channel
Official e-sourcing portal
Electronic submission
Allowed
Accepted languages
en
Detailed submission instructions & authority contactsFrom official release

Please find further details of the project and submit any questions / submit your response to the procurement specific questionnaire (conditions of participation) via our free procurement portal : supplier.in-tend.co.uk/historicengland/home ↗

Please be aware at this Stage 1 (procurement specific questionnaire (conditions of participation)), we do not require a Tender returned. Only the stage 1 document.

Published estimate £149,000 excludes VAT (£178,000 including VAT).

Timeline

9 Oct 2026 → 28 Jan 2027 · 5 dates
  1. Tender notice published18 days ago
    9 Oct 2026, 18:33 BST
  2. Today
    27 Oct 2026
  3. Clarification questions byin 21h
    28 Oct 2026, 17:00 GMT
  4. Submission deadlinein 7 days
    4 Nov 2026, 09:30 GMT
  5. Award decision expected byin 77 days
    12 Jan 2027, 23:59 GMT
  6. Contract startsin 92 days
    28 Jan 2027

Notice history

1 event · 1 release on Find a Tender
  1. Tender notice published
    9 Oct 2026, 18:33 BST
    UK4

Commercial outcome & contract awards

Nothing awarded yet
Awards (0)
No award published
Contracts (0)
No contract published
Bid statistics
No aggregate bid statistics published

Contracting authority & participating public bodies

Historic England

Contracting authorityPublic authority - central government GB-PPON: PXLY-5862-RMML The Engine House, Swindon, South West, SN22EHContact email

Official documents & specifications (1)

Official links; attachments are not copied

Notices published for this procedure

  • Tender notice tenderTender noticeUK4Tender notice on Find a Tender