Published requirement descriptionContract Background
The contract is for single supplier for the provision of Chillers, Air Conditioning Systems and Refrigeration Maintenance Contract at The Pirbright Institute.
Scope of works
Work Package 1 – Chillers, Air Conditioning & Refrigeration Equipment
This works package is for a single supplier to service and or repair all refrigeration, air conditioning and associated systems at The Pirbright Institute.
Service visits should be arranged according to F gas regulations, site requirements and insurance inspections schedules.
The attached schedule (Schedule 5.C - Refrigeration Plant List) details the buildings, the details of the Chillers, Freezers and Air conditioning equipment and frequency of service visits required. A site plan showing the locations and relative sizes of these buildings is included in Schedule 5.D - Site Plan.
The contractor will be expected to advise on the condition of the equipment and provide details of any remedial works required following each service. Critical remedial works should be advised to Pirbright on the same day.
Quotations for non-critical remedial works should be provided to Pirbright within 1 week of a service visit.
The contractor should also allow for the supply of:
- 1 x vacuum pump
- 1 x recovery machine
- 1 x set of gauges
- 1 x refrigerant leak detector
These will be kept in our restricted areas and will only be used by the contractor. These can be taken out of containment and returned to contractor at the end of the contract. This is to prevent the unnecessary passage and time-consuming decontamination for contractor’s tools when work is being done on our contained systems.
Within the first 6 months of the contract the contractor will be expected to provide a critical spares list and an itemised quotation for all systems.
Service reports should be left on site or received by site on the day of the service and test certificates should be received by site within one week of the service visit.
In addition to providing their own access equipment, it is expected that the supplier will include in their works, performing basic tasks required to access equipment such as lifting ceiling panels.
Work Package 2 – Emergency Call out Service
The supplier of works package 1 must also provide a 24-hour emergency call out service. With an engineer site attendance time of under 4 hours. All specification requirements that are associated with work package 1 also apply this work package.
Work Package 3 – Insurance Inspection Facilitation
The contractor will need to allow for the supply of an engineer to aid our insurance inspector with PSSR inspections on chillers. This can take up to 5 days per year.
- The authority expects to re-tender this requirement around 12 Aug 2029, 23:59 BST.
CPV: Air-conditioning appliances · Air-conditioning installation work · Air-conditioning installations · Installation work of refrigeration equipment · Refrigeration coils · Repair and maintenance of plant · Repair and maintenance services of cooler groups · Ventilation and air-conditioning installation work
The lotProcurement structure
single lot · value publishedWhat it takes to wini
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Evaluation split and conditions of participation as published; the tender pack may add morei
How this buyer will score bids.
The evaluation criteria and weights exactly as published on the notice, grouped by family (price, quality, social value and so on).
Published award criteria (2)
- Quality
- Price
- Price carries 40 of 100 points: a 10% discount moves about 4 points. The method statement decides this lot, not the discount.
Price arithmetic assumes straight proportional scoring; the tender pack may use another formula.
Procedure terms & legal framework
From the official record- Procedure method
- Open procedure
- Legal basis
- UKPGA · 2023/54 Procurement Act 2023
- Procurement category
- Services
- Notice status
- Closed
- Procurement threshold
- Above threshold (FTS publication)
- Regulatory regime
- Standard
- Commercial structure
- Stand-alone contract (no framework)
- Competition type
- Competitive procedure
- GPA / WTO covered
- Unspecified in notice
- Recurring procurement
- Yes · next expected 12 Aug 2029
- First published
- 12 Aug 2026, 18:30 BST
- Last source update
- 14 Aug 2026, 11:24 BST
- Award evaluation window
- Submission end – 22 Oct 2026
- FTS notice number
2026/S 000-076986- Latest notice
- Tender notice (UK4)
- Classification (CPV)
- Delivery area
- Not published
- Official registry OCID
ocds-h6vhtk-06e318Find a Tender
How it was run
Official notice- Submission deadline
- 21 Sept 2026, 12:00 BST
- Submission channel
- Official e-sourcing portal
- Electronic submission
- Allowed
- Accepted languages
- en
Timeline
12 Aug 2026 → 1 Nov 2026 · 5 dates- Tender notice published77 days ago12 Aug 2026, 18:30 BST
- Latest notice published75 days ago14 Aug 2026, 11:24 BST
- Submission deadline37 days ago21 Sept 2026, 12:00 BST
- Award decision expected by6 days ago22 Oct 2026, 23:59 BST
- Today29 Oct 2026
- Contract startsin 2 days1 Nov 2026
Notice history
2 events · 2 releases on Find a Tender · since 12 Aug 2026- Tender notice published12 Aug 2026, 18:30 BSTUK4
- Tender notice published14 Aug 2026, 11:24 BSTUK4
Contracting authority & participating public bodies
Official documents & specifications (3)
Official links; attachments are not copiedTender pack and attachments
- Bidding documents and specifications The ITT Pack can be viewed via https://in-tendhost.co.uk/thepirbrightinstitute/aspx/Home
Notices published for this procedure
- Tender notice Tender notice on Find a Tender
- Tender notice Tender notice on Find a Tender