North Portsea Coastal Scheme - Phase 5: Ports Creek
Authority: Portsmouth City Council (Local council)
What is being bought
Published requirement descriptionPortsmouth City Council, 'the council', is inviting applications from suitably qualified applicants & contractors for the construction and delivery of a continuing major programme of coastal defence construction to deliver a flood and coastal erosion risk management (FCERM) scheme at Ports Creek, Portsmouth, UK; located to the north of Portsea Island (AKA 'Ports Creek').
Ports Creek is phase 5 of the North Portsea Coastal Scheme FCERM scheme. (see website for more details coastalpartners.org.uk/project/north-portse… ↗) which provides a 1 in 500-year standard of protection with a design life of 100 years.
The design consists of an earth bund with a rock armour toe. As this phase will be carried out in an area known for its green, open spaces, the secondary focus of this scheme will be enhancing the natural feel of the area by planting more trees and improving access along the frontage.
The location reference for the approximate centre of the works is '50.83606305284935, -1.0640957680322936'.
The estimated value for construction works is £22.3million.
It is envisaged that the form of contract used will be NEC4 Engineering and Construction Contract (ECC) Option C. The exact form of contract will be confirmed within the tender documents.
The site access and target construction commencement date for the works is 2nd September 2024 with a completion date of 31st August 2026, with the defects date 52 weeks after completion.
The procurement process will be in accordance with the Restricted Procedure as set out within the Public Contracts Regulations (2015).
Application is via completion of a Supplier Selection Questionnaire (SQ) and associated documentation which must be submitted by 26th February at 12:00 noon.
The council intends to invite the top 5 shortlisted contractors to submit a tender return.
The council is targeting an award contract date of 26th July 2024.
The council plans to run this procurement according to the following timetable:
- Issue Supplier Questionnaire - Thursday 25th January 2024
- SQ Clarification deadline - Friday 16th February 2024 at 23:59
- SQ returns - Monday 26th February 2024 at 12 noon
- Notify contractors of SQ results - Thursday 14th March 2024
- Issue Tender - Monday 25th March 2024
- Tender Clarification deadline - Monday 13th May 2024 at 23:59
- Tender returns - Friday 24th May 2024 at 12 noon
- Notify of award - Monday 15th July 2024
- Standstill Period - Monday 15th July - Thursday 25th July 2024
- Contract award - Friday 26th July 2024
- Site access - Monday 2nd September 2024
The deadline for clarifications is 16th February 2024 (23:59) and the deadline for submission of SQ submissions is 26th February at 12:00 noon via the Council's e-sourcing system InTend, which is accessible via: intendhost.co.uk/portsmouthcc/aspx/home ↗
The system will be used to administrate the procurement process in its entirety, guidance documentation is available via the link above.
CPV: Coastal-defence works · Construction work for water projects · Demolition, site preparation and clearance work · Excavating and earthmoving work · Footpath construction work · Forestry services · Horticultural services · Landscape architectural services · Siteworks
The lotProcurement structure
single lot · value publishedLot #1The proposed coastal defence works at Ports Creek involve the construction of an earth…Published value£22,300,000
The proposed coastal defence works at Ports Creek involve the construction of an earth embankment with a rock revetement toe. It also includes consolidation and partial removal of existing defence structures and associated works. In some instances, redundant structures will be removed and appropriately reused or disposed of, to minimise foreshore encroachment, for the benefit of the wider environment. The current defences are made up of multiple structures, generally comprising of mass concrete filled oil drums along with dilapidated seawalls formed of mass concrete/block/masonry.
The main works take place between the eastern side of the Portsbridge Roundabout through to the Network Rail bridge. The works consist of constructing a sloping revetment with a raised earth embankment along most of the frontage.
Other ancillary works include: piling around an outfall, path construction, concrete works to an existing slipway and tying into Network Rail land and working to Network Rail constraints in this area. The Contractor will have to work with Network Rail and follow an agreed safe method of working when in the vicinity of the railway line bridge.
ECI
In line with industry practice the council's designer (Royal HaskoningDHV (RHDHV)) has sought and obtained early contractor involvement input from JT Mackley in order to inform aspects of design, work method, site establishment and management, programme & costings.
The council is satisfied that prior involvement of ECI contractor is compliant with the conditions set out within sub section 5 of Public Contract Regulation 2015. However, the council will provide summarised information concerning the ECI activities and associated outputs within the tender documents that will be issued to the short listed tenderers.
Core Scope of Works
In summary the works will generally consist of:
- Site mobilisation and set up
- Vegetation clearance (including mature trees) and site clearance and access ways
- Construction of earth embankments fronted with rock revetments for scour protection
- Installation of flex MSE retaining walls
- Improvements to existing slipway structure and encasement of existing bridge abutment
- Ensuring existing services are accommodated in the works (e.g outfalls)
- General reinstatement, with high specification public realm enhancements and landscaping
Due to the impact of the scheme, engagement with local businesses, leaseholders and the general public has been undertaken. To date the scheme has received a mostly positive response.
The project is subject to funding from the Environment Agency and there is currently a shortfall in respect of the current funding. However the council is working with the funder & is confident that funding required will be secured in principle prior to issue of the tender & fully secured prior to award of contract.
Procedure terms & legal framework
From the official record- Procedure method
- Restricted procedure
- Legal basis
- CELEX · 32014L0024 Public Contracts Regulations 2015 (Directive 2014/24/EU)
- Procurement category
- Works
- Notice status
- Closed
- Procurement threshold
- Unspecified in notice
- Regulatory regime
- Standard
- Commercial structure
- Stand-alone contract (no framework)
- Competition type
- Competitive procedure
- GPA / WTO covered
- Yes (GPA)
- Recurring procurement
- No (one-off requirement)
- First published
- 25 Jan 2024, 17:21 GMT
- Last source update
- 25 Jan 2024, 17:21 GMT
- FTS notice number
2024/S 000-002645- Classification (CPV)
- Delivery area
- Official registry OCID
ocds-h6vhtk-0434afFind a Tender
How it was run
Official notice- Submission deadline
- 26 Feb 2024, 12:00 GMT
- Submission channel
- {"electronicSubmission"}
- Accepted languages
- en
Timeline
25 Jan 2024 → 25 Mar 2024 · 3 dates- Notice published25 Jan 2024, 17:21 GMT
- Submission deadline26 Feb 2024, 12:00 GMT
- Invitations to tender expected25 Mar 2024
Contracting authority & participating public bodies
Dispute resolution & review bodies
- The High Court of JusticeReview body
Official documents & specifications
Official links; attachments are not copiedNo document links were published on the notice.