Derby College Group: Contract Register & Procurement Profile

DfE school register: Further educationEducationEast MidlandsDerby

Official UK PPONPHCR-9151-PMNLWebsitederby-college.ac.uk ↗

Open now1next deadline 30 Oct 2026
i

Tenders you can still bid for.

Notices at tender stage whose deadline has not passed, counted the way the search counts them: a notice shows under every code and region it names.

Notices, last 12 months13+63% vs prior 12 months (8)
i

Notices published in the last 12 months.

Counted per tender, not per lot, against the 12 months before where shown.

Typical bids per lot7.525% single-bid · 4 bid reports
i

How many companies usually bid when this buyer runs a tender.

Middle value of the bid counts on its award notices, one per lot. Only real competitions count: direct awards and framework places are left out.

Based on 4 lots from this buyer’s competitions, last 24 months. Small sample.

Last 24 months, all categories.

Contracts ending ≤18 months1none within 6 months
i

Contracts that finish in the next 18 months.

Contracts ending in that window by the published end date or, where only a duration is published, an estimate from signature plus duration (marked). Neither, not counted.

An end date does not confirm a new procurement.

Published award value, 24m£237knet · on 2 of 2 published values · top 5 = 100%
i

How much this buyer has awarded recently, by published values.

Sum of published VAT-exclusive awards to single suppliers, last 24 months. Left out: concession revenue, framework ceilings, repeated notices, equal-value duplicates.

Published values, not actual spend. The biggest rows are listed so you can check.

Open notices

1 live · deadline in the future or not published · as of page build

What they buy
i

What kind of work is bought here.

Notices by procurement category (CPV). A notice with several categories counts in each.

Last 24 months · CPV divisions on published procedures · a notice with several divisions counts in each

How they buy
i

How work here is packaged.

Notices by commercial tool: a single contract, a framework, or a dynamic purchasing system.

Last 24 months · 21 notices · commercial tool and route as published on the notice, not a legal-regime claim

Commercial tool
i

How work here is packaged.

Notices by commercial tool: a single contract, a framework, or a dynamic purchasing system.

  • Contract95%(20 notices)
    20 of 21 notices are Contract (95%).
  • Framework5%(1 notice)
    1 of 21 notices is Framework (5%).
Procedure route
i

Which procedures buyers here use.

Notices by the procedure they declare: open, selective, limited or direct. Open and selective are competitions; limited and direct are not.

  • Open90%(19 notices)
    19 of 21 notices are Open (90%).
  • Selective5%(1 notice)
    1 of 21 notices is Selective (5%).
  • Route not published5%(1 notice)
    1 of 21 notices is Route not published (5%).
Typical bids per lot
i

How many companies usually bid when this buyer runs a tender.

Middle value of the bid counts on its award notices, one per lot. Only real competitions count: direct awards and framework places are left out.

Based on 4 lots from this buyer’s competitions, last 24 months. Small sample.

Last 24 months, all categories.

7.5moderate · n=425% of lots drew a single bid
Deadline → award
i

How long this buyer takes to decide after bids close.

Middle value in days from the bid deadline to the award date, on this buyer’s own tenders.

Based on 6 decided tenders across all categories, last 24 months.

Last 24 months.

57 daysrobust · n=6
Notice amendments
i

How often this buyer changes a notice after publishing it.

Middle number of amendments per notice. Deadline extensions and corrections both count.

Based on 21 notices across all categories, last 24 months.

Last 24 months.

08 of 21 notices amended
Award vs estimate
i

Do this buyer’s awards land above or below its own estimates.

Each lot’s published estimate against its award, on this buyer’s competitions, like for like.

Based on 2 lots with both an estimate and an award, last 24 months. Small sample.

A past pattern, not a price to bid.

Last 24 months.

42.6% below estimateindicative · n=2

Who wins here
i

Which suppliers win the most here.

Suppliers ranked by the number of tenders won, not by money. A supplier on one big framework with many call-offs does not outrank one that won many separate competitions.

All published awards naming a supplier · ranked by distinct procedures, not pounds · panel and call-off entries inflate award records

SupplierProceduresShareLast 24mAward recordsLast activity
Compartment Fire Ltd228.6%227 Nov 2025
Nottinghamshire and Derbyshire Traction Company Limited114.3%1110 Jul 2026
Operam Education Group t/a Provision Recruitmentframework/DPS on 1114.3%1111 Jul 2025
SKILLS COLLEGE UK LIMITED114.3%1120 Jul 2026
Exede Ltd (T/A Xede Recruitment)framework/DPS on 1114.3%1111 Jul 2025
Think FE Limitedframework/DPS on 1114.3%1111 Jul 2025
Axis Recruitment Limitedframework/DPS on 1114.3%1111 Jul 2025
Reed Specialist Recruitment Limited,framework/DPS on 1114.3%1111 Jul 2025

7 awarded procedures across 16 suppliers: too few to describe concentration.

Published award value (24m)
i

How much this buyer has awarded recently, by published values.

Sum of published VAT-exclusive awards to single suppliers, last 24 months. Left out: concession revenue, framework ceilings, repeated notices, equal-value duplicates.

Published values, not actual spend. The biggest rows are listed so you can check.

£237kSum of published VAT-exclusive values on 2 of 2 published single-supplier values; the five largest make 100%; a further 3 published a VAT-inclusive amount only, kept apart.
Largest published awards
i

The biggest published awards.

Awards to a single supplier with a published value, largest first, so you can check the totals against the notice.

A repeated framework total can appear here. Open the notice to check.

SupplierAwardedTermPublished value
Firedoor works to include supply, installation, remedial repair and PPMCompartment Fire Ltd7 Nov 20253 mo · up to 2.8 yrs£153,487
Condition Surveys for Derby College GroupHartnell Taylor Cook LLP—7 mo£83,450 †

Contracts ending
i

Contracts that finish in the next 18 months.

Contracts ending in that window by the published end date or, where only a duration is published, an estimate from signature plus duration (marked). Neither, not counted.

An end date does not confirm a new procurement.

3 of 3 contracts carry an end date · not a retender forecast

Recent procedures

Latest 22 of 22 procedures where this authority buys, is the authority the work is for, or runs the procurement

ProcedureStatusPublishedPublished value
Provision of a Financial Management SystemBusiness transaction and personal business software packageOpen24 Aug 2026£0
Plumbing Room Workshop and Classroom Alterations at the Roundhouse Stephenson BuildingRefurbishment workAwarded / complete6 Aug 2026£100,000
Subcontract Adult Skills Fund ProvisionAdult and other education servicesAwarded / complete20 Jul 2026£6,500,000
Provision of a student transport (bus) serviceHire of buses and coaches with driverAwarded / complete14 Jul 2026£1,560,000
The Hudson Building Extension ProjectBuilding construction workOpen9 Jul 2026£3,900,000
Refurbishment of Toilet Facilities at the RoundhouseOverhaul and refurbishment workOpen29 May 2026£100,000
Pre-market Engagement for Finance SystemAccounting software packagePlanning1 May 2026£350,000
Provision of Roller Shutters, Automatic Doors & Car Park Barriers/Gates “barrier systems worksBuilding installation workOpen3 Apr 2026£0
Provision of Man-safe or personal fall protection systemsFencingOpen3 Apr 2026£0
Provision of Catering ServicesCanteen and catering servicesAwarded / complete24 Mar 2026£9,000,000
Condition Surveys for Derby College GroupArchitectural and building-surveying servicesAwarded / complete19 Feb 2026£100,000
Firedoor planned preventative maintenance, remedial repairs and installation worksBuilding installation workAwarded / complete12 Feb 2026£260,000
Broomfield Hall and Annexe Refurbishment WorksBuilding completion workOpen12 Feb 2026£1,100,000
Recruitment Agency FrameworkFramework3 lotsBusiness services: lawAwarded / complete17 Dec 2025£3,500,000
Firedoor works to include supply, installation, remedial repair and PPMBuilding installation workAwarded / complete24 Nov 2025£260,000
Provision of Catering ServicesCanteen and catering servicesCancelled21 Nov 2025£9,000,000
Shower block at Joseph Wright CentreOverhaul and refurbishment workOpen29 Sept 2025£170,000
Mechanical and Electrical refurbishment works - Lathkilldale and KirtleyCentral-heating boilersOpen13 May 2025£606,000
Animal Care Minor Building, Roofing and Refurbishment worksAgricultural buildings construction workOpen12 May 2025£312,000
Internal and external decorating Summer 2025Decorating suppliesOpen25 Apr 2025£140,000

Search all 22 procedures for this authority →

About this data
  • Source. Official UK public procurement notices (Find a Tender), reused under the Open Government Licence v3.0. New notices arrive through the day; the figures are rebuilt nightly.
  • One profile per authority. Different spellings and registration numbers of the same body are merged into this profile. It includes tenders the authority ran for other bodies and tenders run on its behalf; spend is credited to the body that pays.
  • Values are published values. Award values are what the authority published, excluding VAT and framework ceilings. They are not a budget or total spend.
  • Contract end dates. 3 of 3 published contracts have an end date; 0 of those are estimated as the signature (or publication) date plus the published duration and are marked “estimated”. They feed “Contracts ending”, the same rule as the retender radar.
  • Every figure shows what it rests on. Not every notice publishes a bid count, a value or a delivery region, so each figure carries the number of records behind it, and one built on few records is marked as such. The on a figure explains it; the counting rules are in the methodology. Spotted something wrong? Tell us.